MAINTENANCE/CALIBRATION

!

 

Important: 

All valves must have the position calibrated after installation. 

NOTE:

 If using an EB_J or EB_S butterfly valve refer to ”Valve Polarity“ in the Programming Mode 

section on page 21. This programming must be done before performing the automatic valve position 

calibration.

Automatic Valve Position Calibration for APEX-S

The valve position calibration determines the point where the valve is fully open or fully 

closed. This process will automatically determine these points by running the valve to the fully 

closed position then the fully open position, and then back to the fully closed position. This 

calibration must be done after installation, when the actuator has been replaced, or in any 

case when valve does not fully close or fully open.

NOTE: 

These routines must be utilized so the position of the valve will be displayed accurately.

Valve Calibration (CODE 1113)

1  Turn on power to the valve and controller(s) 
  Enter Code 1113
2  Press and hold the CLOSE button; then press and hold the OPEN button  After 5 seconds, the red 

CLOSE LED will flash  Code 1113 can now be entered  

3  Use the OPEN button to set the first digit of the code 1113  Press the OPEN button once, one 

green LED on 

 

4  Press the CLOSE button to move the cursor to the next digit for the second digit to be entered  

Press the OPEN button once, one green LED on 

 

5  Press the CLOSE button to move the cursor to the next digit for the third digit to be entered  
 

6  Press the CLOSE button to move the cursor to the next digit for the fourth digit to be entered  

Press the OPEN button three times  Valve calibration begins approximately 4 to 5 seconds after 

the last digit is entered for Code 1113 

 
7  The valve will move to the closed position, calibrate to the closed position, then move to the open 

position, calibrate that position and then return back to the closed position and stop  While the 

valve is calibrating the LEDs on the controller will turn on and off on at a time from left to right  

When calibration is complete all 11 LEDs will flash several times and then the red closed LED will 

stay on solid  The valve is now position calibrated 

Summary of Contents for APEX-S

Page 1: ...98607000 REV rel Valve Controller Installation Operating Maintenance Instructions 1 574 295 8330 www elkhartbrass com...

Page 2: ...onents 6 Controls and Indicators 7 INSTALLATION 8 Install Valve Controller 8 ELECTRICAL CONNECTIONS 10 Wiring the Valve Controller 12 MAINTENANCE CALIBRATION 17 Automatic Valve Position Calibration fo...

Page 3: ...9 Figure 3 Valve Controller Wiring 10 Figure 4 Valve Actuator Wiring 11 Figure 5 Wiring Cables and Connectors 13 Figure 6 Wiring Cables and Connectors 14 Figure 7 APEX S 1 1 Wiring Connections 15 Fig...

Page 4: ...s Features 10 Green LEDs Indicate Open Valve Position Red LED Indicates Valve is Closed Keypad rubberized large embossed and color coded Tactile Buttons glove friendly Button actions Full Open Full Cl...

Page 5: ...ecifications APEX S Valve Controller Supply Voltage 9 30VDC Current 0 5 A Display Module only Fuse Rating 1 A 12V 0 5 AMPS 24V Dimensions Height 3 31 32 Width 3 5 8 Depth 2 5 16 Datalink Interface CAN...

Page 6: ...ions of 3 31 32 inches high by 3 5 8 inches wide by 2 5 16 inches deep All controls and indicators are located on the front of the module Refer to Controls and Indicators Valve with Actuator An Elkhar...

Page 7: ...en LEDs will turn on one at a time from left to right until all 10 of the green LEDs light up indicating the valve is fully open Valve Control Buttons Two buttons open and close the valve The third bu...

Page 8: ...s Refer to Figure 2 for layout and dimensions 2 Cut out a mounting hole according to the cutout diagram in Figure 2 and drill three holes clearance or tapped for 10 mounting screws 3 Connect the cable...

Page 9: ...2 Valve Controller Mounting Dimensions 2 5 16 29 3 32 Recommended Panel Cutout 10 clear thru bolt with nut or tapped for 10 fasteners 3x 2 3 32 2 3 32 1 3 64 2 9 16 1 9 32 3 1 16 R 1 2 1 17 32 3 5 8...

Page 10: ...NNECTIONS Figure 3 Valve Controller Wiring Valve Controller 6 Pin Connector Pin Signal Description 1 Power 12 24VDC 2 Ground Supply 3 NC 4 Datalink Shield 5 Datalink CAN Low 6 Datalink CAN High Pin 1...

Page 11: ...2 Ground 3 Valve Position 5VDC 4 Valve Position Ground 5 Valve Position Signal 6 Valve Control 7 Valve Control 8 CLOSE 9 PRESET 10 OPEN 11 Datalink CAN High 12 Datalink CAN Low 12 Pin Connector Pin 1...

Page 12: ...valve see diagram on page 16 1 Connect power and ground to the controllers Use 1 amp fuse for 12v 0 5 amp for 24v positive controller leads 2 Connect CAN wiring from the first APEX S to a CAN splitte...

Page 13: ...12VDC GND Red Black Cable A Display Cables withTerminating Resistor P N 37542000 12 Pin Plug Connector 2 Pin Connector Butt Splice Connectors To APEX S Valve Controller 12VDC GND Red Black Cable C Va...

Page 14: ...Resistor P N 375440NT Connectors 3 Pin Plug Connector Cable E APEX Extension Cable P N 37543002 2 P N 37543010 10 P N 37543015 15 P N 37543020 20 P N 37543030 30 P N 37543040 40 To APEX Valve Controll...

Page 15: ...15 APEX SWiring 1 1 Connections Figure 7 APEX S 1 1 Wiring Connections A C E...

Page 16: ...16 APEX SWiring 2 1 Connections Figure 8 APEX S 2 1 Wiring Connections A A E E F D Replaces CAN Lead with termination...

Page 17: ...ess and hold the CLOSE button then press and hold the OPEN button After 5 seconds the red CLOSE LED will flash Code 1113 can now be entered 3 Use the OPEN button to set the first digit of the code 111...

Page 18: ...k Inspect the valve controller wiring and valve for damage Operate all possible functions to ensure that each works normally Fully open and fully close valve to check for full range operation During v...

Page 19: ...ve will travel to that position and stop there To program a preset position move the valve to the desired position full closed of full open or anywhere in between then press and hold the preset button...

Page 20: ...h time the OPEN button is pressed the next LED will illuminate 2 Press the CLOSE button to move the cursor to the next digit Now all LEDs will be off and ready for the second digit to be entered Press...

Page 21: ...ss the OPEN button once one green LED on 4 Press the CLOSE button to move the cursor to the next digit All LEDs will be off Press the OPEN button 6 times six green LEDs on 5 After 3 seconds the LEDs w...

Page 22: ...or Probable Cause Symptom Corrective Actions A One LED blinking alternatively on the left and right sides No Valve Detected Verify the ID is Set Correctly Verify the Wiring B Left and right LEDs blink...

Page 23: ...23...

Page 24: ...khart Brass Manufacturing Co Inc 1302 W Beardsley Avenue Elkhart IN 46514 Tel 574 295 8330 Toll Free 800 346 0250 Fax 574 293 9914 www elkhartbrass com Email eb info safefleet net 98607000 REV rel 11...

Reviews: