27/01/22
User Manual TPS/T 10-90kVA 62000560_09_
25
4.
INSTALLATION
4.1.
GENERAL NOTES
4.1.1.
INSPECTION
After unpacking the product, please inspect any damage that may have occurred during the
shipment. Save all packing materials in case the product has to be returned one day. If any
damage is found, please file a claim with the carrier immediately. Do not return the product to the
factory without obtaining the prior Return Merchandise Authorization (RMA) acceptance from
ELETTROTEST SPA.
4.1.2.
Line Connection
The TPS/T galvanic insulation from the electrical line allows to consider the TPS/T like a
transformer so The TPS/T must be protect from with a differential and Magneto-thermic
protection both in input and output.
For the installer is required to strictly respect of the current regulations for this particular
installation.