Product handling on the construction site
Transport
The fire dampers are transported to the
construction site with a forklift or crane
with a lifting fork. To avoid damage, they
must be lifted, not dragged and never lo-
wered hard against the ground.
Reception and inspection
of the delivery
The fire dampers are inspected imme-
diately when the delivery arrives at the
workplace. The inspection is to check that
the delivery corresponds to the order and
the consignment note. The approved deli-
very is acknowledged on the consignment
note. Products with defects or defects
must not be installed. Contact the supplier
immediately.
Storage
The storage of materials on the site should
be planned so that you get the least pos-
sible internal transport. The fire dampers
must be protected against water and
always stored in a dry place. Furthermore,
they must be handled so that no mechani-
cal damage occurs to them.
Commissioning
The fire dampers must not be put into use
until the entire installation is in operational
condition.
– Damage due to incorrect transport,
handling or storage.
– That the user has failed to inspect,
maintain and to a reasonable extent
take care of the equipment.
– Personal injury or property damage as
a result of using the product in violation
of the instructions and specifications in
this manual.
EKOVENT AB hereby disclaims all responsibility for:
EKOVENT:s liability shall be limited to repair
or replacement of faulty equipment part.