3
INSTALL IN THE CENTRE OF CEILING AT LEAST 300mm FROM
LIGHT FITTINGS & WALLS
ENSURE MAINS POWER IS CORRECTLY CONNECTED TO L & N
TERMINALS ON ALL INTERCONNECTED ALARMS - OTHERWISE
UNITS WILL BE DAMAGED
DO NOT FIT ACTUAL ALARMS UNTIL ALL BUILDING WORK IS
COMPLETED TO AVOID CONTAMINATION. AFTER CHECKING
OPERATION, COVER ALARMS WITH DUST COVER UNTIL
REQUIRED FOR USE
HIGH VOLTAGE INSULATION TESTS CAN BE APPLIED TO
MOUNTING PLATES ONLY. ALARM HEADS
MUST
BE REMOVED
DO NOT ATTEMPT TO OPEN THE ALARM AS IT IS PERMANENTLY
SEALED FOR SAFETY
INTERCONNECT ALL ALARMS