4
Installation and commissioning
4.4
Installing the ecoBatterySystem
Prerequisites
➯
The ecoBatterySystem is in position (see chapter 4.2).
➯
All ecoBatteryModules are installed (see chapter 4.3).
Procedure
1. Install the cables for external connections, such as the charging station, domestic grid and
electric boiler, by running them along the designated cable ducts and connect them (see
chapter 9.1 "Connection diagram (example)").
INFORMATION
Secure the strain relief correctly.
2. Connect the ecoFirewall to:
°
Power supply
°
ecoBatterySystem
°
Network connection (Internet)
Example of an installation at a customer site
A
ecoFirewall power supply
B
ecoBatterySystem / PLC (ECOCOACH)
C
Network connection (INTERNET)
INFORMATION
•
There is no power outlet for the ecoFirewall in the ecoBatterySystem.
•
The ecoFirewall should be installed outside of the ecoBatterySystem.