background image

Operating instructions

W4D450-JA18-40

Translation of the original operating instructions

4.5 Opening additional cable glands

Fig. 1: Cable gland opening

NOTE
Tightness and strain relief are dependent on the cable
used.

→ This must be checked by the user.

4.6 Checking connections

;

Ensure isolation from supply (all phases).

;

Make sure a restart is impossible

;

Check the cables for proper fit.

4.7 Switching on the device

The device may only be switched on if it has been installed properly and
in accordance with its intended use, including the required safety
mechanisms and professional electrical hookup. This also applies for
devices which have already been equipped with plugs and terminals or
similar connectors by the customer.

WARNING
Hot motor housing

Risk of fire
→ Ensure that no combustible or flammable materials are

located close to the fan.

;

Before switching on, check the device for visible external damage
and make sure the protective devices are functional.

;

Check the fan's air flow paths for foreign matter and remove any
foreign matter found.

;

Apply the nominal supply voltage.

NOTE
Damage to the device from vibration

Bearing damage, shorter service life
→ Low-vibration operation of the fan must be ensured over the

entire speed control range.

→ Severe vibration can arise for instance from inexpert

handling, transportation damage and resultant imbalance or
be caused by component or structural resonance.

→ Speed ranges with excessively high vibration levels and

possibly resonant frequencies must be determined in the
course of fan commissioning.

→ Either run through the resonant range as quickly as

possible with speed control or find another remedy.

→ Operation with excessively high vibration levels can

lead to premature failure.

4.8 Switching off the device

;

Disconnect the device from the power supply at the supply line's
main switch.

;

When disconnecting, be sure to disconnect the ground connection last.

5. MAINTENANCE, MALFUNCTIONS, POSSIBLE
CAUSES AND REMEDIES

Do not perform any repairs on your device. Send the device to ebm-
papst for repair or replacement.

WARNING
Live terminals and connections even with device
switched off

Electric shock
→ Wait five minutes after disconnecting the voltage at all poles

before opening the device.

CAUTION
The motor restarts automatically when operating voltage
is applied, e.g. after a power failure.

Risk of injury
→ Keep out of the device's danger zone.
→ When working on the device, switch off the line voltage

and ensure that it cannot be switched back on.

→ Wait until the device comes to a stop.
→ Install the externally wired thermal overload protector in

the control circuit so that following a malfunction the motor
does not switch on again automatically after cooling off.

NOTE

If the device is not operated for a lengthy period in installed
condition in a dry environment, it is to be started up and
operated at full speed for one hour at least every four months. If
the device is not operated for a lengthy period in installed
condition in a damp environment (e.g. outdoors), it is to be
started up and operated at full speed for at least two hours once
a month to move the bearings and allow any condensate that
may have ingressed to evaporate.

Malfunction/fault

Possible cause

Possible remedy

Impeller not
running smoothly

Imbalance in rotating
parts

Clean the device;
replace it if imbalance
persists after cleaning.
Make sure no
weight clips are
removed during
cleaning.

Motor not turning

Mechanical blockage

Switch off, isolate
from supply and
remove mechanical
blockage.

Line voltage faulty

Check line voltage,
restore power supply.

Faulty connection

Isolate from supply,
correct connection;
see connection
diagram.

Item no. 15647-5-9970 · ENU · Change 220358 · Approved 2021-02-23 · Page 10 / 12

ebm-papst Mulfingen GmbH & Co. KG · Bachmühle 2 · D-74673 Mulfingen · Phone +49 (0) 7938 81-0 · Fax +49 (0) 7938 81-110 · [email protected] · www.ebmpapst.com

Summary of Contents for W4D450-JA18-40

Page 1: ...aff Only authorized specialists are permitted to install the device to carry out a test run and to perform work on the electrical installation 1 3 Basic safety rules 1 1 3 Basic safety rules The safet...

Page 2: ...ion levels occur following installation appropriate shielding measures have to be taken by the user NOTE Electrical or electromagnetic interference after installing the device in customer equipment Ve...

Page 3: ...prohibited and could be hazardous Operating the device in an unbalanced state e g due to dirt deposits or ice formation Resonant operation operation with severe vibration This also includes vibration...

Page 4: ...duct drawing All dimensions in mm 1 Airflow direction V 2 Cable silicone 9G 0 5 mm 9x crimped splices Item no 15647 5 9970 ENU Change 220358 Approved 2021 02 23 Page 4 12 ebm papst Mulfingen GmbH Co K...

Page 5: ...ginal operating instructions All dimensions in mm Item no 15647 5 9970 ENU Change 220358 Approved 2021 02 23 Page 5 12 ebm papst Mulfingen GmbH Co KG Bachm hle 2 D 74673 Mulfingen Phone 49 0 7938 81 0...

Page 6: ...tandardized measurement setup 3 4 Technical description Weight 11 96 kg Size 450 mm Motor size 94 Rotor surface Painted black Blade material Sheet steel painted black Fan housing material PP plastic G...

Page 7: ...of physical injury such as back injuries Two people should work together to remove the device from its packaging CAUTION The blades of the impeller could be damaged Carefully set down the fan on a so...

Page 8: ...se control Depending on the type of installation of the device noise and vibration may also occur in the case of phase control Vibration can lead to bearing damage and thus premature failure Heating u...

Page 9: ...tion Y Star connection L1 U1 black L2 V1 blue L3 W1 brown W2 yellow U2 green V2 white TOP 2x gray PE green yellow Item no 15647 5 9970 ENU Change 220358 Approved 2021 02 23 Page 9 12 ebm papst Mulfing...

Page 10: ...switch When disconnecting be sure to disconnect the ground connection last 5 MAINTENANCE MALFUNCTIONS POSSIBLE CAUSES AND REMEDIES Do not perform any repairs on your device Send the device to ebm paps...

Page 11: ...e 5 2 Safety inspection What to check How to check How often What action Contact protection cover for intactness or damage Visual inspection At least every 6 months Repair or replacement of device Dev...

Page 12: ...xternal rotor motors from ebm papst Mulfingen GmbH Co KG Ferrite magnets can be disposed of in the same way as normal iron and steel Electrical insulating materials on the product in cables and wires...

Reviews: