Operating instructions
R3G800-AQ03-01
Translation of the original operating instructions
Fig. 1: Recommended stripping lengths in mm (inside the terminal box)
Legend: CL = control lines
4.3.2 Connecting cables with terminals
WARNING
Terminals and connections have voltage even with a
unit that is shut off
Electric shock
→ Wait five minutes after disconnecting the voltage at all poles
before opening the device.
;
Remove the cap from the screwed cable gland.
Remove the cap only in those places where cables are inserted.
;
Insert the line(s) (not included in the standard scope of delivery) into
the terminal box.
;
First connect the "PE" (protective earth) connection.
;
Connect the lines to the corresponding terminals.
Use a screwdriver to do so.
During the connection work, ensure that no cables splice off.
Fig. 2: Connecting the wires to terminals
;
Seal the terminal box.
4.3.3 Cable routing
No water may penetrate along the cable in the direction of the cable gland.
When routing the cable, ensure that the screwed cable glands are
arranged at the bottom. The cables must always be routed downwards.
Fig. 3: Cable routing for fans installed upright.
Item no. 52101-5-9970 · ENG · Revision 82539 · Release 2014-05-08 · Page 7 / 12
ebm-papst Mulfingen GmbH & Co. KG · Bachmühle 2 · D-74673 Mulfingen · Phone +49 (0) 7938 81-0 · Fax +49 (0) 7938 81-110 · [email protected] · www.ebmpapst.com