Fig. 5: Cleaning of the fan with a high-pressure cleaner.

;

Maximum water pressure 80 bar

;

Minimum clearance between water outlet and fan 40 cm

;

The water jet must be aimed perpendicularly to the blades.

;

If possible, only aim the water jet at the rotating parts.

;

Do not aim the water jet directly at the condensation drainage hole (if
applicable).

;

When cleaning the electronics housing, do not aim the water jet
directly at the terminal box cover or cable glands.

;

If there is a condensation drainage hole in the rotor, make sure this is
not blocked by dirt.

;

Completely remove any cleaning agents used.

;

If severe corrosion is visible on load-bearing or rotating parts, switch
off the device immediately and replace it.

;

Repair of load-bearing or rotating parts is not permitted!

;

Operate the fan for 2 hours at maximum speed so that any water that
has ingressed can evaporate.

;

If cleaning does not eliminate vibrations, the fan may need to be
rebalanced. To have it rebalanced, contact ebm-papst.

;

The fan is equipped with maintenance-free ball bearings. The lifetime
lubrication of the ball bearings is designed for a service life of 40,000
hours.

;

If bearing replacement is necessary after that period, contact ebm-
papst.

;

Adapt the maintenance intervals to the actual level of dust exposure.

6.2 Safety inspection

NOTE
High-voltage test

The integrated EMC filter has Y capacitors. The tripping current
is exceeded when AC testing voltage is applied.
→ Test the device with DC voltage when you perform the

legally required high-voltage test. The voltage to be used
corresponds to the peak value of the AC voltage required by
the standard.

What to check

How to check

How often

What action?

Contact
protection
cover for
intactness or
damage

Visual inspection At least every

6 months

Repair or
replacement of
device

Device for
damage to
blades and
housing

Visual inspection At least every

6 months

Replacement of
device

Fastening the
cables

Visual inspection At least every

6 months

Fasten

Insulation of
cables for
damage

Visual inspection At least every

6 months

Replace cables

Tightness of
cable gland

Visual inspection At least every

6 months

Retighten,
replace if
damaged

Condensation
drainage holes
for clogging,
where necessary

Visual inspection At least every

6 months

Open holes

Welds for crack
formation

Visual inspection At least every

6 months

Replace device

Abnormal
bearing noise

acoustic

At least every
6 months

Replace device

6.3 Disposal

For ebm-papst, environmental protection and resource preservation are
top priority corporate goals.
ebm-papst operates an environmental management system which is
certified in accordance with ISO 14001 and rigorously implemented
around the world on the basis of German standards.
Right from the development stage, ecological design, technical safety
and health protection are fixed criteria.
The following section contains recommendations for ecological disposal
of the product and its components.

6.3.1 Country-specific legal requirements

NOTE
Country-specific legal requirements

Always observe the applicable country-specific legal
regulations with regard to the disposal of products or waste
occurring in the various phases of the life cycle. The
corresponding disposal standards are also to be heeded.

6.3.2 Disassembly

Disassembly of the product must be performed or supervised by
qualified personnel with the appropriate technical knowledge.
The product is to be disassembled into suitable components for disposal
employing standard procedures for motors.

WARNING
Heavy parts of the product may drop off. Some of the
product components are heavy. These components
could drop off during disassembly.

This can result in fatal or serious injury and material damage.
→ Secure components before unfastening to stop them falling.

Item no. 51471-5-9970 · ENU · Change 209539 · Approved 2021-02-12 · Page 14 / 15

ebm-papst Mulfingen GmbH & Co. KG · Bachmühle 2 · D-74673 Mulfingen · Phone +49 (0) 7938 81-0 · Fax +49 (0) 7938 81-110 · [email protected] · www.ebmpapst.com

Summary of Contents for A3G710-AU21-35

Page 1: ...ecialists are permitted to install the device to carry out a test run and to perform work on the electrical installation 1 3 Basic safety rules 1 1 3 Basic safety rules The safety hazards associated w...

Page 2: ...system machine wait until all parts have come to a standstill DANGER Ejected parts Missing protective devices may cause balancing weights or broken fan blades to be ejected and cause injuries Take app...

Page 3: ...e In particular operating the device in the following ways is prohibited and could be hazardous Operating the device in an unbalanced state e g due to dirt deposits or ice formation Resonant operation...

Page 4: ...ion of air flow A 2 Max clearance for screw 25 mm 3 Cable diameter min 4 mm max 10 mm tightening torque 4 0 6 Nm 4 Tightening torque 3 5 0 5 Nm Item no 51471 5 9970 ENU Change 209539 Approved 2021 02...

Page 5: ...mined using a motor impeller combination in a standardized measurement setup 3 4 Technical description Weight 25 6 kg Size 710 mm Motor size 150 Rotor surface Painted black Electronics housing materia...

Page 6: ...r than or equal to 120 times the rated output of the arrangement 4 CONNECTION AND STARTUP 4 1 Mechanical connection CAUTION Cutting and crushing hazard when removing fan from packaging Carefully remov...

Page 7: ...necessary to connect an additional protective earth conductor by way of the extra protective earth terminal provided on the device The protective earth terminal is located on the housing and provided...

Page 8: ...ed in scope of delivery into the terminal box First connect the PE protective earth Connect the wires to the corresponding terminals Use a screwdriver to do so When connecting ensure that no wire ends...

Page 9: ...e for the device by ebm papst Mode parameter set 1 PWM control Mode parameter set 2 PWM control Fan device address 1 Max PWM 100 Min PWM 5 1 Save set value to EEPROM Yes Set value requirement Analog l...

Page 10: ...contact changeover contact common connection contact rating 250 VAC max 2 A AC1 min 10 mA KL2 3 NC Status relay floating status contact break for failure KL 3 1 RSA Bus connection RS485 RSA MODBUS RTU...

Page 11: ...EEPROM setting the integrated controller s direction of action can be selected via bus or digital input Din3 normal pin open or applied voltage 5 50 VDC inverse bridge to GND or applied voltage 1 VDC...

Page 12: ...supply Switching off the device for maintenance Switch off the device via the control input Do not switch the motor e g in cyclic operation on and off via power supply Disconnect the device from the p...

Page 13: ...e for at least 25 s and then switch it on again Alternatively reset the error message by applying a control signal of 0 5 V to Din1 or by shorting Din1 to GND In the event of further malfunctions cont...

Page 14: ...pection At least every 6 months Replacement of device Fastening the cables Visual inspection At least every 6 months Fasten Insulation of cables for damage Visual inspection At least every 6 months Re...

Page 15: ...xternal rotor motors from ebm papst Mulfingen GmbH Co KG Ferrite magnets can be disposed of in the same way as normal iron and steel Electrical insulating materials on the product in cables and wires...

Reviews: