Translation of the original operating instructions

4.3 Connecting the cables

The device has external leads.

;

First connect the "PE" (protective earth).

Connect the cables according to your application. When doing so,
observe Chapter 4.4 Connection diagram.

4.3.1 Cable routing

Water must be prevented from reaching the cable exit along the cable.

NOTE
Damage caused by moisture penetration.

Moisture can penetrate into the terminal box if water is
constantly present at the cable glands.
→ To prevent the constant accumulation of water at the cable

glands, the cable should be routed in a U-shaped loop
wherever possible.

→ If this is not possible, a drip edge can be produced by

fitting a cable tie directly in front of the cable gland for example.

Fans installed upright

Fig. 1: Cable routing for fans installed upright. The cables must always
be routed downward.

Item no. 10833-5-9970 · ENU · Change 202174 · Approved 2018-12-27 · Page 7 / 10

ebm-papst Mulfingen GmbH & Co. KG · Bachmühle 2 · D-74673 Mulfingen · Phone +49 (0) 7938 81-0 · Fax +49 (0) 7938 81-110 · [email protected] · www.ebmpapst.com

Summary of Contents for A2E200-AF02-02

Page 1: ... and otherwise used by suitably qualified trained and authorized technical staff Only authorized specialists are permitted to install the device to carry out a test run and to perform work on the electrical installation 1 3 Basic safety rules 1 1 3 Basic safety rules The safety hazards associated with the device must be assessed again following installation in the final product The locally applica...

Page 2: ... coming into contact with the rotor or the impeller Secure the device against accidental contact Before working on the system machine wait until all parts have come to a standstill WARNING Rotating device Long hair and dangling items of clothing jewelry and the like can become entangled and be pulled into the device Injuries can result Do not wear any loose fitting or dangling clothing or jewelry ...

Page 3: ...ting the device in an unbalanced state e g due to dirt deposits or ice formation Resonant operation operation with severe vibration This also includes vibration transmitted to the fan from the customer installation Operation in medical equipment with a life sustaining or life support function Conveying solids in the flow medium Painting the device Connections e g screws coming loose during operati...

Page 4: ...ll dimensions in mm 1 Direction of air flow A 2 Max clearance for screw 5 mm 3 Cable PVC 4G 0 5 mm 4x crimped splices Item no 10833 5 9970 ENU Change 202174 Approved 2018 12 27 Page 4 10 ebm papst Mulfingen GmbH Co KG Bachmühle 2 D 74673 Mulfingen Phone 49 0 7938 81 0 Fax 49 0 7938 81 110 info1 de ebmpapst com www ebmpapst com ...

Page 5: ...roval CCC EAC With regard to cyclic speed loads note that the rotating parts of the device are designed for a maximum of one million load cycles If you have special questions consult ebm papst for support Use the device in accordance with its degree of protection Information on surface quality The surfaces of the products conform to the generally applicable industrial standard The surface quality ...

Page 6: ...th an all pole disconnection switch 4 2 1 Requirements Check whether the information on the nameplate matches the connection data If the motor run capacitor was not installed by ebm papst check whether the information on the motor run capacitor matches the information on the nameplate Before connecting the device make sure the power supply matches the device voltage Only use cables designed for th...

Page 7: ... the terminal box if water is constantly present at the cable glands To prevent the constant accumulation of water at the cable glands the cable should be routed in a U shaped loop wherever possible If this is not possible a drip edge can be produced by fitting a cable tie directly in front of the cable gland for example Fans installed upright Fig 1 Cable routing for fans installed upright The cab...

Page 8: ...uctions 4 4 Connection diagram U1 blue Z brown U2 black PE green yellow Item no 10833 5 9970 ENU Change 202174 Approved 2018 12 27 Page 8 10 ebm papst Mulfingen GmbH Co KG Bachmühle 2 D 74673 Mulfingen Phone 49 0 7938 81 0 Fax 49 0 7938 81 110 info1 de ebmpapst com www ebmpapst com ...

Page 9: ...n your device Send the device to ebm papst for repair or replacement WARNING Live terminals and connections even with device switched off Electric shock Wait five minutes after disconnecting the voltage at all poles before opening the device CAUTION Electric charge on capacitor after device is switched off Electric shock risk of injury Discharge the capacitors before working on the device CAUTION ...

Page 10: ...ments NOTE Country specific legal requirements Always observe the applicable country specific legal regulations with regard to the disposal of products or waste occurring in the various phases of the life cycle The corresponding disposal standards are also to be heeded 5 3 2 Disassembly Disassembly of the product must be performed or supervised by qualified personnel with the appropriate technical...

Reviews: