3. Installation
3.3 Mounting
3.3.2 Front mounting XV-303
Securing the panel with Holding bracket with set screw
List of tools:
l
2.0 mm Allen key
l
PZ2 Pozidriv screwdriver
l
Torque wrench with Newton meter scale
The required holding brackets are included in the right amount as accessories with the
HMI panel. All the included holding brackets need to be installed!
Together with the Polyurethane foam gasket, this holding bracket is the main element
involved in achieving an IP65 (front) degree of protection.
The purpose of the holding brackets is to secure the XV300 onto a control panel, etc.
To this end, the brackets must be hooked into the enclosure sideways and screwed
against the control panel door, etc.
Make sure to position the holding brackets in such a way that they will push against the
center of the peripheral Polyurethane foam gasket.
Pre-install the holding brackets using the set screws.
Check that the gasket is
in its correct position and
pre-install the holding
brackets
Screw the set screws into the
holding brackets
Insert the holding brackets into the
enclosure
Peripheral Polyurethane
foam gasket along the
entire edge
Material Raku-PUR 31-
3117 black, dimensions
2mm x 3mm (0.0787" x
0.1181")
Figure 15: Pre-installing the
holding brackets
Internal hexagon M4x25 DIN
914 galvanized
Figure 16: Mounting the XV-303
XV300
12/15 MN048017 EN www.eaton.eu
37