Installation
4-34
Eaton
®
Power Xpert
®
9395C UPS Installation and Operation Manual P-164000821—Rev 01
www.eaton.com/powerquality
4.9
Installing Options, Accessories, and Distributed Bypass Control Wiring
4.10
Initial Startup
Startup and operational checks must be performed by an authorized Eaton Customer Service Engineer, or the
warranty terms specified on page W-1 become void. This service is offered as part of the sales contract for the
UPS. Contact an Eaton service representative in advance (usually a two-week notice is required) to reserve a
preferred startup date.
4.11
Completing the Installation Checklist
The final step in installing the UPS system is completing the following Installation
Checklist. This checklist ensures that you have completely installed all hardware, cables, and other equipment.
Complete all items listed on the checklist to ensure a smooth installation. Make a copy of the Installation
Checklist before filling it out, and retain the original.
After the installation is complete, an Eaton Customer Service Engineer must verify the operation of the UPS
system and commission it to support the critical load. The service representative cannot perform any
installation tasks other than verifying software and operating setup parameters. Service personnel may request
a copy of the completed Installation Checklist to verify all applicable equipment installations have been
completed.
NOTE
The Installation Checklist MUST be completed prior to starting the UPS system for
the first time.
Summary of Contents for Power Xpert Series
Page 2: ......
Page 23: ...Section I Installation...
Page 24: ......
Page 93: ...Section II Operation...
Page 94: ......
Page 155: ......
Page 156: ...P 164000821 1 P 164000821 1...