Installation Plan and Unpacking
Use the following basic sequence of steps to install the UPS:
1.
Create an installation plan for the battery cabinet (Chapter 3).
2.
Prepare your site for the battery cabinet (Chapter 3).
3.
Inspect and unpack the battery cabinet (Chapter 3).
4.
Unload and install the battery cabinet, and wire the system (Chapter 4).
5.
Complete the Installation Checklist (Chapter 4).
6.
Have authorized service personnel perform preliminary operational checks and
startup.
NOTE
Startup and operational checks must be performed by an authorized Eaton Customer Service
Engineer, or the warranty terms specified on page W-1 become void. This service is offered as part of the
sales contract for the UPS. Contact service in advance (usually a two-week notice is required) to reserve a
preferred startup date.
3.1
Creating an Installation Plan
Before installing the battery cabinet, read and understand how this manual applies to
the system being installed. Use the procedures and illustrations in paragraph 3.2 and
Chapter 4 to create a logical plan for installing the system.
3.2
Preparing the Site
For the battery system to operate at peak efficiency, the installation site should meet
the environmental parameters outlined in this manual. If the UPS is to be operated at
an altitude higher than 1500m (5000 ft), contact your service representative for
important information about high altitude operation. The operating environment must
meet the weight, clearance, and environmental requirements specified.
3.2.1
Environmental and Installation Considerations
The battery system installation must meet the listed guidelines. Failure to follow
guidelines may void your warranty.
S
The system must be installed on a level floor suitable for computer or electronic
equipment.
S
If perforated floor tiles are required for ventilation, place them in front of the
battery cabinet.
S
The system must be installed in a temperature and humidity controlled indoor area
free of conductive contaminants.
S
The battery cabinet is to be installed in a
standalone
configuration.
S
The recommended installation location for battery cabinets located adjacent to the
UPS is on the right side of the UPS cabinet. This location will allow for future
expansion using an external module.
Figure