background image

Instruction Manual 

 

Pow-R-Line Retrofit Panelboards 

Page 

8   

 

 

 

Effective: November 2007 

P1R & P2R Retrofit  Panels 

                                                        

 

For more information visit: www.EatonCanada.ca               

 

                                                                     

11/2007 

 

leaflets that are shipped with each panelboard 
containing GFP or contact Eaton Electrical. 

 

Preparing Panelboard for 
Insulation/Megger Testing 

Devices Installed with Control Power 
Fusing 

Devices, which require control power fusing, can be 
easily damaged beyond repair if not disconnected 
during the testing phase. These devices include, but 
are not limited to, customer metering equipment, 
electronic breaker trip units, motor operators and 
communication equipment.  Prior to testing the 
panelboard, turn off all control power devices in the 
panelboard to prevent damage to components.  The 
control power may be turned off by utilizing the 
control power switch or by removing the fuses. 
Components that use power supplies include 
customer metering and certain breaker accessories 
and these must be isolated before testing. 
 

 

TO PREVENT DAMAGE TO GROUND FAULT 
CONTROL CIRCUITS, METERING CIRCUITS, 
TRANSIENT VOLTAGE SURGE PROTECTION 
(TVSS) OR OTHER CONTROL CIRCUITS, WHEN 
MEGGERING PANELBOARD, ISOLATE 
CIRCUITS FROM PANELBOARD SYSTEM 
BEFORE BEGINNING THE MEGGER 
OPERATION. BE SURE TO RECONNECT THOSE 
CIRCUITS AFTER MEGGER TESTS ARE 
COMPLETED. 
NOTE: SOME GROUND FAULT CIRCUITS MAY 
NOT BE FUSED, THEREFORE ISOLATION OF 
THOSE CIRCUITS REQUIRES DISCONNECTING 
WIRING FROM BUS BARS. 
 

 

DO NOT TEST A CIRCUIT BREAKER WHILE IT’S 
IN SERVICE AND ENERGIZED. 
 
 
 

 

TESTING OF A CIRCUIT BREAKER THAT 
RESULTS IN THE TRIPPING OF THE CIRCUIT 
BREAKER SHOULD BE DONE ONLY WHEN THE 
PANELBOARD IS DE-ENERGIZED. 

 

 
FAILURE TO SHORT OR DISCONNECT DURING 
PANELBOARD TESTING WILL RESULT IN 
FAILURE OF ELECTRONIC COMPONENTS. 
 
 

DISCONNECT POWER AT SOURCE BEFORE 
REMOVING OR INSTALLING FUSES.   
HAZARDOUS VOLTAGE. WILL CAUSE SEVERE 
INJURY OR DEATH. 
Failure to disconnect control power during 
panelboard testing will result in failure of 
electronic components and void manufacturer’s 
warranty.

 

 

Pre-Energizing Panelboard 
Insulation Testing 

 
Exercise extreme care to prevent the 
equipment from being connected to the power 
source while tests are being conducted. 
 

Prior to energizing the panelboard, perform a 
Megger or DC test of the panelboard’s insulation 
with the neutral isolated from the ground and the 
switches and/or circuit breakers open, conduct 
electrical insulation resistance tests from phase to 
phase, phase to ground, phase to neutral, and 
neutral to ground. Retain results for use to compare 
to results produced in the future.  Prior to testing, 
remove all control power fusing and connections to 
products, which will be damaged in this test. See 
above. 

DO NOT USE AC Dielectric 
testing. 

Test resulting in readings at or above 1 megaohm 

is satisfactory. 

Post-Testing 

After testing, and with the panelboard de-energized, 
reconnect all devices, control fusing and 
disconnects removed prior to testing.  

Securing the Panelboard 

Install the dead front cover and trim parts on the 
panelboard using hardware supplied by the 
manufacturer. Take caution that conductors are not 
pinched between parts when installing the dead-
front cover and trim.  All parts should be aligned and 
secured when installed.  
Do not leave holes or gaps in the dead-front 
construction.  
Clean up any debris in and around the panelboard. 

 

FAILURE TO DISCONNECT CONTROL POWER 
DURING PANELBOARD TESTING WILL RESULT 
IN FAILURE OF ELECTRONIC COMPONENTS. 

 

IL01417001E

Summary of Contents for Pow-R-Line P2R Series

Page 1: ...els For more information visit www EatonCanada ca Contents INSTALLATION CRITERIA 2 SAFETY MEASURES 3 PRE INSTALLATION RECEIVING HANDLING AND STORAGE 4 REMOVAL OF EXISTING PANELBOARD INTERIOR 4 INSTALL...

Page 2: ...er BAB 30 60 100 26 5 14 25 4 5 Breaker BAB 42 60 100 33 5 14 25 4 5 Breaker E or F Frame 18 60 225 30 14 25 4 5 Breaker E or F Frame 30 60 225 36 14 25 4 5 Breaker E or F Frame 42 60 225 42 14 25 4 5...

Page 3: ...ons of this custom built product Eaton Electrical has made all reasonable efforts to ensure that the instructions in this document are adequate and free of material errors and omissions Eaton Electric...

Page 4: ...SHOULD INSTALL AND OR SERVICE THIS EQUIPMENT Removal of Existing Panelboard Interior DO NOT work on electrical equipment while energized Verify power entering the equipment is de energized at the sou...

Page 5: ...t compromising wire bending space requirements as listed in the Appendix Table 1 Ensure that electrical clearance requirements are maintained per NECTM CECTM Care must be taken to ensure that the trim...

Page 6: ...Never clip cable wire strands in order to fit within connectors If cable wire does not match the rating of the connector contact the manufacturer Use an antioxidant compound if required Insert bare c...

Page 7: ...lly inspect panelboard insulators bus bar and conductors for damage DO NOT ENERGIZE IF DAMAGE IS FOUND Contact Eaton Electrical Circuit Breakers Circuit breakers are typically shipped in either the op...

Page 8: ...DE ENERGIZED FAILURE TO SHORT OR DISCONNECT DURING PANELBOARD TESTING WILL RESULT IN FAILURE OF ELECTRONIC COMPONENTS DISCONNECT POWER AT SOURCE BEFORE REMOVING OR INSTALLING FUSES HAZARDOUS VOLTAGE...

Page 9: ...ns in downstream equipment 3 Verify and follow the sequence of energizing circuits and loads Verify phase sequencing on loads such as motors which can be damaged or destroyed by incorrect phase connec...

Page 10: ...ces metering equipment and other components Damage to insulation and other surface materials can occur Do Not Use Compressed Air in cleaning Maintenance after Cleaning After cleaning perform a second...

Page 11: ...t a series of inspections be made at quarterly intervals until the progressive effects of local conditions can be analyzed to determine a regular schedule Panelboard Events and Service Interruptions S...

Page 12: ...rials and tools from the equipment Inspect all connections for damage and torque Re install all covers fillers dead front assemblies and side sheets Conduct panelboard insulation resistance testing de...

Page 13: ...for Copper or Aluminum Bus Bar Connections Bolt Size Torque Inch Lbs Torque Foot Lbs 10 30 2 5 65 5 4 5 16 130 10 8 3 8 240 20 600 50 National Electrical Code and NEC are registered trademarks of the...

Page 14: ...P2R Retrofit Panels For more information visit www EatonCanada ca 11 2007 Notes 2007 Eaton Corporation All Rights Reserved Printed in Canada Publication No PUB50895 November 2007 Eaton Yale Company 5...

Reviews: