Installation Checklist
-
All packing materials and restraints have been removed from each cabinet.
-
Each cabinet in the UPS system is placed in its installed location.
-
A cabinet grounding/mounting kit is installed between the ISBM and UPM sections.
-
All conduits and cables are properly routed to the UPS and any ancillary cabinets.
-
All power cables are properly sized and terminated.
-
Battery cables are terminated on E4 (+) and E5 (–).
-
Battery aux contact signal wiring is connected from the UPS to the battery disconnect.
-
Battery shunt trip signal wiring is connected from the UPS to the battery disconnect. (OPTIONAL)
-
LAN drops are installed.
-
All LAN connections have been completed.
-
A ground conductor is properly installed.
-
Air conditioning equipment is installed and operating correctly.
-
The area around the installed UPS system is clean and dust‐free. (It is recommended that the UPS be installed on a
level floor suitable for computer or electronic equipment.)
-
Adequate workspace exists around the UPS and other cabinets.
-
Adequate lighting is provided around all UPS equipment.
-
A 120 Vac service outlet is located within 7.5 meters (25 feet) of the UPS equipment.
-
The REPO device is mounted in its installed location and its wiring is terminated inside the UPS cabinet.
-
The normally-closed (NC) Emergency Power-off contact (pins 1 and 2 on TB1) is jumpered if not used.
-
Alarm relays and building alarms are wired appropriately. (OPTIONAL)
-
A remote battery disconnect is mounted in its installed location and its wiring is terminated inside the UPS.
(OPTIONAL)
-
Accessories are mounted in installed locations and wiring is terminated inside the UPS cabinet. (OPTIONAL)
-
The debris shields covering the UPS cabinet ventilation grills are removed.
-
Startup and operational checks are performed by an authorized Eaton Customer Service Engineer.