Eaton BladeUPS 5 kVA to 60 kVA (N+1) User’s Guide 164201649—Rev 14
69
Figure 51. Installing the UPS Mounting Brackets
6-32 Flat-Head
Screws
Mounting Bracket
12. Slide the UPS into the rack.
13.
Parallel or parallel-ready system only.
If you are installing other X-Slot cards besides the Powerware Hot
Sync CAN Bridge Card, skip to step 16.
NOTE
Leaving the UPS unattached allows you to adjust the UPS position in the rack for any
clearance needed to install the X-Slot cards.
14. Using four M5 machine screws, secure the front of the cabinet to the rack as shown.
Figure 52. Securing the Front of the UPS
Position 9
Position 4
M5 Screws
15. Insert the two rear hold-down brackets on the rails into the slots on the rear of the cabinet.
a.
If necessary, push out on the rack upright to allow the clearance needed to insert the bracket. The
rack upright flexes easily.
b.
Verify that the brackets seat firmly, then tighten the nuts on the rear hold-down brackets. The UPS is
now secured in the rack.
Summary of Contents for BladeUPS none
Page 8: ...viii Eaton BladeUPS 5 kVA to 60 kVA N 1 User s Guide 164201649 Rev 14 Table of Contents ...
Page 12: ...xii Eaton BladeUPS 5 kVA to 60 kVA N 1 User s Guide 164201649 Rev 14 List of Figures ...
Page 14: ...xiv Eaton BladeUPS 5 kVA to 60 kVA N 1 User s Guide 164201649 Rev 14 List of Tables ...
Page 20: ...6 Eaton BladeUPS 5 kVA to 60 kVA N 1 User s Guide 164201649 Rev 14 Introduction ...
Page 134: ...120 Eaton BladeUPS 5 kVA to 60 kVA N 1 User s Guide 164201649 Rev 14 Metering ...
Page 160: ...16420164914 164201649 14 ...