Eaton BladeUPS 5 kVA to 60 kVA (N+1) User’s Guide 164201649—Rev 14
65
•
Mounting brackets and fasteners (if not already installed):
–
(2) mounting brackets
–
(8) 6-32 flat-head screws
•
Rails and fasteners:
–
(2) sliding rail assemblies (left and right)
–
(2) rear hold-down brackets
–
(16) M5 machine screws
–
(8) M5 clip nuts for racks with round holes
–
(8) M5 cage nuts for racks with square holes
–
(8) M6 hex nuts with integrated washers
Parallel system only.
Verify that the following items are included with each Powerware Hot Sync
CAN Bridge Card:
•
CAN Bridge Card cable with (2) RJ-45 connectors
•
Redundant signal cable with (2) two-position terminal block connectors
•
(2) blue terminating plugs
44..1100
R
Raacckk S
Seettuupp ffoorr tthhee U
UP
PS
S
CAUTION
The UPS is heavy. Removing the UPS from its carton requires a minimum of two people. Use the corrugated
lifting sling (packaged with the UPS) to move the UPS.
NOTE
Mounting rails are required for each individual cabinet.
To install the UPS rail kit:
1.
Select the proper holes in the rack for positioning the UPS in the rack.
NOTE 1
The UPS rails take up position 1 through position 12. The UPS will take up 6U or 18 total
hole positions.
NOTE 2
Verify that the hole patterns on the rails and mounting brackets align with the hole
pattern on the rack.
Summary of Contents for BladeUPS none
Page 8: ...viii Eaton BladeUPS 5 kVA to 60 kVA N 1 User s Guide 164201649 Rev 14 Table of Contents ...
Page 12: ...xii Eaton BladeUPS 5 kVA to 60 kVA N 1 User s Guide 164201649 Rev 14 List of Figures ...
Page 14: ...xiv Eaton BladeUPS 5 kVA to 60 kVA N 1 User s Guide 164201649 Rev 14 List of Tables ...
Page 20: ...6 Eaton BladeUPS 5 kVA to 60 kVA N 1 User s Guide 164201649 Rev 14 Introduction ...
Page 134: ...120 Eaton BladeUPS 5 kVA to 60 kVA N 1 User s Guide 164201649 Rev 14 Metering ...
Page 160: ...16420164914 164201649 14 ...