Eaton BladeUPS 5 kVA to 60 kVA (N+1) User’s Guide 164201649—Rev 14
WARNING
•
Servicing should be performed by qualified service personnel knowledgeable of batteries and required
precautions. Keep unauthorized personnel away from batteries.
•
Batteries can present a risk of electrical shock or burn from high short circuit current. Observe the
following precautions: 1) Remove watches, rings, or other metal objects; 2) Use tools with insulated
handles; 3) Do not lay tools or metal parts on top of batteries, 4) Wear rubber gloves and boots.
•
When replacing batteries, replace with the same type and number of batteries or battery packs. Contact
your service representative to order new batteries.
•
Proper disposal of batteries is required. Refer to your local codes for disposal requirements.
•
Never dispose of batteries in a fire. Batteries may explode when exposed to flame.
•
Do not open or mutilate the battery or batteries. Released electrolyte is harmful to the skin and eyes and
may be extremely toxic.
•
Determine if the battery is inadvertently grounded. If inadvertently grounded, remove source from ground.
Contact with any part of a grounded battery can result in electrical shock. The likelihood of such shock can
be reduced if such grounds are removed during installation and maintenance (applicable to equipment and
remote battery supplies not having a grounded supply circuit).
•
ELECTRIC ENERGY HAZARD. Do not attempt to alter any battery wiring or connectors. Attempting to alter
wiring can cause injury.
•
Disconnect charging source prior to connecting or disconnecting battery terminals.
77..66
H
Hoow
w ttoo R
Reeppllaaccee EEB
BM
Mss
CAUTION
The EBM is heavy ). Lifting the cabinet into the rack requires a minimum of two people.
To replace the EBMs:
1.
Switch all battery circuit breakers to the OFF (O) position (see See
).
2.
Unplug the EBM cable from the UPS.
If additional EBMs are installed, unplug the EBM cable from the battery connector on each EBM.
3.
If not already installed, install the supplied mounting brackets on the new EBM.
4.
Replace the EBM. See
Recycling the Used Battery or UPS
for proper disposal.
5.
Plug the new EBM into the UPS as shown in
.
For additional EBMs, plug the EBM cable into the battery connector on the adjacent EBM.
6.
Remove the breaker tie from the circuit breaker on all EBMs.
7.
Switch all battery circuit breakers to the ON ( |) position.
Summary of Contents for BladeUPS none
Page 8: ...viii Eaton BladeUPS 5 kVA to 60 kVA N 1 User s Guide 164201649 Rev 14 Table of Contents ...
Page 12: ...xii Eaton BladeUPS 5 kVA to 60 kVA N 1 User s Guide 164201649 Rev 14 List of Figures ...
Page 14: ...xiv Eaton BladeUPS 5 kVA to 60 kVA N 1 User s Guide 164201649 Rev 14 List of Tables ...
Page 20: ...6 Eaton BladeUPS 5 kVA to 60 kVA N 1 User s Guide 164201649 Rev 14 Introduction ...
Page 134: ...120 Eaton BladeUPS 5 kVA to 60 kVA N 1 User s Guide 164201649 Rev 14 Metering ...
Page 160: ...16420164914 164201649 14 ...