background image

600 A T-OP II™ terminator operation instructions

1

Operation Instructions

   MN650047EN   May 2017

CAUTION 

Eaton’s Cooper Power series 600 A T-OP II™ terminator 

is designed to be operated in accordance with normal 

safe operating procedures . These instructions are not 

intended to supersede or replace existing safety and 

operating procedures . Terminators must be de-energized 

during operation or maintenance . Visible break and 

adequate grounding must be provided before cable 

work proceeds .

T-OP II terminators should be installed and serviced only 

by personnel familiar with good safety practice and the 

handling of high-voltage electrical equipment .

General

Equipment required

1 Voltage Tester

3 Grounding Elbows

3 T-OP II insulated Standoff Bushings

3 T-OP II insulated Protective Caps

1 Hotstick

Personal Protective Equipment

Insulating Rubber Blanket

Silicone Grease

Figure 1 .  600 A T-OP  II Terminator

Figure 2 .  One-line diagram of a three-phase cable connected to a three-phase switch on either end

200 A PROTECTIVE CAP

LOADBREAK TAP 

REDUCING PLUG 

(LRTP)

URD CABLE

T-OP II TERMINATOR ASSEMBLY

APPARATUS BUSHING

Figure 3 .  Line illustration of the T-OP II

Summary of Contents for 600 A 35 kV Class Insulated Standoff Bushing

Page 1: ...600 A T OP II terminator operation instructions COOPER POWER SERIES Deadbreak Apparatus Connectors MN650047EN Effective May 2017 Supersedes March 1995 S600 12 1...

Page 2: ...OSE OR MERCHANTABILITY OTHER THAN THOSE SPECIFICALLY SET OUT IN ANY EXISTING CONTRACT BETWEEN THE PARTIES ANY SUCH CONTRACT STATES THE ENTIRE OBLIGATION OF EATON THE CONTENTS OF THIS DOCUMENT SHALL NO...

Page 3: ...SCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITY I SAFETY FOR LIFE III SAFETY INFORMATION III Safety instructions iii GENERAL 1 Equipment required 1 OPERATION 2 Isolating and grounding a cable requi...

Page 4: ...d high voltage lines and equipment and support our Safety For Life mission Safety information DANGER Hazardous voltage Contact with hazardous voltage will cause death or severe personal injury Follow...

Page 5: ...proceeds T OP II terminators should be installed and serviced only by personnel familiar with good safety practice and the handling of high voltage electrical equipment General Equipment required 1 Vo...

Page 6: ...4 De energized cables Step 2 Determine that cables are de energized Remove 200 A protective cap or arrester from T OP II terminators using hotstick and set aside in a clean protected area Insert test...

Page 7: ...orque tool clockwise to make the threaded connection turn until tight Remove O T Torque tool Figure 8 Move T OP II Terminator to insulated bushing Step 4 Provide a visible ground After securing cable...

Page 8: ...ing Grasp pulling eye of the grounding elbow with shotgun pull firmly to remove elbow from the LRTP of the T body Set elbow aside in a clean area Grasp O T Torque tool with the shotgun and pull fully...

Page 9: ...Instructions MN650047EN May 2017 Figure 14 Reinstall 200 a protective cap Repeat this procedure for all cables on both ends that were previously grounded Remove all tools grounds and personal protect...

Page 10: ...600 A T OP II terminator operation instructions 6 Operation Instructions MN650047EN May 2017 This page intentionally left blank...

Page 11: ...600 A T OP II terminator operation instructions 7 Operation Instructions MN650047EN May 2017 This page intentionally left blank...

Page 12: ...nited States Eaton com cooperpowerseries 2017 Eaton All Rights Reserved Printed in USA Publication No MN650047EN May 2017 Eaton is a registered trademark All trademarks are property of their respectiv...

Reviews: