600 A T-OP II™ terminator operation instructions
1
Operation Instructions
MN650047EN May 2017
CAUTION
Eaton’s Cooper Power series 600 A T-OP II™ terminator
is designed to be operated in accordance with normal
safe operating procedures . These instructions are not
intended to supersede or replace existing safety and
operating procedures . Terminators must be de-energized
during operation or maintenance . Visible break and
adequate grounding must be provided before cable
work proceeds .
T-OP II terminators should be installed and serviced only
by personnel familiar with good safety practice and the
handling of high-voltage electrical equipment .
General
Equipment required
●
●
1 Voltage Tester
●
●
3 Grounding Elbows
●
●
3 T-OP II insulated Standoff Bushings
●
●
3 T-OP II insulated Protective Caps
●
●
1 Hotstick
●
●
Personal Protective Equipment
●
●
Insulating Rubber Blanket
●
●
Silicone Grease
Figure 1 . 600 A T-OP II Terminator
Figure 2 . One-line diagram of a three-phase cable connected to a three-phase switch on either end
200 A PROTECTIVE CAP
LOADBREAK TAP
REDUCING PLUG
(LRTP)
URD CABLE
T-OP II TERMINATOR ASSEMBLY
APPARATUS BUSHING
Figure 3 . Line illustration of the T-OP II