Fig. 3  Meter Module Assembly and End Cap Locations

EXTENDED

END CAP

FLUSH

END CAP

MAIN BUS

JOINT BOLTS

 

-20

 SCREWS

MAIN

DEVICE

BUS END CAPS:

Install the bus end caps on the left hand side of the far left

meter module in the assembly and the far right meter

module in the assembly.  End caps are supplied on the

main switch, main circuit breaker, or main terminal box

(one flush cap and one extended cap). (See Fig. 3 below).

PROVISIONS FOR HUBS OR KNOCKOUTS:

- Top Connections - Outdoor Application (1MM & 3MM)

   Knockouts are not provided in top endwall.  Punch proper

   holes as required.  Install raintight hubs on outdoor

   devices.

- Top Connections - Indoor Application (1MM & 3MM)

   Use the knockouts in top of module as required.

- Top Connections - Indoor or Outdoor Applications

      (35MM, 37MM, 35SS, 37SS)

   Remove raintight plate and punch proper holes for

   installing raintight hubs.  Reinstall raintight plate and

   install raintight hubs into the raintight plate.

- Top Connections - Indoor or Outdoor Applications

      (MTB, MFS, MCB, MHCB, or BPS)

   Knockouts are not provided in top endwall.  Punch proper

   holes as required.  Install raintight hubs on outdoor

   devices.

PROVISIONS FOR HUBS OR KNOCKOUTS (CONT’D):

- Recheck all main bus joint bolts for tightness.  Torque to

   300 lb-in. (33.90 N-m).

- Recheck all phase connectors for tightness.  Torque to

   60 lb-in. (6.78 N-m) minimum.

- Check all wire and cable terminations for proper installation

   and tightness of lugs.

- Clean interiors of all units to remove foreign construction

   material.

- Reinstall all meter socket covers and tenant breaker

   covers.

TESTING AND INSPECTION:

I.L. 70-8306

2

- Backwall Connection (1MM & 3MM)

   Knockouts are provided in Meter Modules.  Remove

   selected knockouts and pull wire through knockout

   openings.

- Backwall Connection (35MM, 37MM, 35SS, 37SS)

   Knockouts are provided in Meter Modules.  Remove

   selected knockouts and pull wire through knockout

   openings.

PHASE

CONNECTORS

MAIN

DEVICE

- Bottom Connection (1MM & 3MM)

   Indoor and outdoor applications use knockouts that are

   provided in bottom of meter modules or main devices.

- Bottom Connection (35MM, 37MM, 35SS, 37SS)

   Indoor and outdoor applications use knockouts that are

   provided in bottom of meter modules or main devices.

Phase connectors are factory installed on the A Phase &

B Phase bus.  Remove appropriate phase connectors and

balance for Phase A-B, B-C, or A-C, as needed, across

several meter modules in a complete installation. Torque

all phase connectors to 60 lb-in (6.78 N-m). (See Fig. 4

above).

PHASE BALANCING, 3 PHASE SYSTEM (3MM ONLY):

Fig. 4  Knockout Locations and Phase Connections

TOP KNOCKOUT PLATE

OR RAINTIGHT PLATE

RAINTIGHT

PLATE

BOTTOM

KNOCKOUT

PLATE

Use only the circuit breakers listed on the meter module.

Check amperage and interrupting capacity for the

application.

INSTALL AND WIRE TENANT CIRCUIT BREAKERS: