Installation
Eaton
®
Power Xpert 9395 Integrated Battery Cabinet (Model 1085 and 1085HR) Installation Manual 164201687—Rev 06
www.eaton.com/powerquality
4-17
Figure 4-15. 1085HR Battery String Connection
4.4
Initial Startup
Startup and operational checks must be performed by an authorized Eaton Customer Service Engineer, or the
warranty terms specified on page W-1 become void. This service is offered as part of the sales contract for the
UPS. Contact service in advance (usually a two-week notice is required) to reserve a preferred startup date.
4.5
Completing the Installation Checklist
The final step in installing the battery cabinet is to complete the Installation Checklist. This checklist ensures all
hardware, cables, and other equipment have been installed. Completing all items on the checklist will ensure
a smooth installation. Make a copy of the Installation Checklist before filling it out, and retain the original.
After completing your installation, a service representative will be able to verify the operation of the battery
cabinet and commission it to support the critical load. The service representative cannot perform any
installation tasks other than verifying that the battery cabinet has been correctly installed. Service personnel
may request a copy of the completed Installation Checklist to be sure all applicable equipment installation
requirements have been completed.
Battery Breaker
Fixed Battery Power
Connector (black)
String Connectors
(black with blue lock)
The Installation Checklist MUST be completed prior to starting the battery system for the first time.