Installation Plan and Unpacking
Use the following basic sequence of steps to install the UPS:
1.
Create an installation plan for the battery cabinet (Chapter 3).
2.
Prepare your site for the battery cabinet (Chapter 3).
3.
Inspect and unpack the battery cabinet (Chapter 3).
4.
Unload and install the battery cabinet, and wire the system (Chapter 4).
5.
Complete the Installation Checklist (Chapter 4).
6.
Have authorized service personnel perform preliminary operational checks and start up the system.
3.1
Creating an Installation Plan
Before installing the battery cabinet, read and understand how this manual applies to the system being
installed. Use the procedures and illustrations in paragraph 3.2 and Chapter 4 to create a logical plan for
installing the system.
3.2
Preparing the Site
For the UPS system to operate at peak efficiency, the installation site should meet the environmental
parameters outlined in this manual. If the UPS is to be operated at an altitude higher than 1000m (3300 ft),
contact an Eaton service representative for important information about high altitude operation. The operating
environment must meet the weight, clearance, and environmental requirements specified.
3.2.1
Environmental Considerations
The battery system installation must meet the listed guidelines. Failure to follow guidelines may void your
warranty.
l
The system must be installed on a level floor suitable for computer or electronic equipment.
l
If perforated floor tiles are required for ventilation, place them in front of the battery cabinet.
l
The system must be installed in a temperature and humidity controlled indoor area free of conductive
contaminants.
l
The battery cabinet is to be installed in a
standalone
configuration.
l
The recommended installation location for battery cabinets located adjacent to the UPS is on the right side
of the UPS cabinet. This location will allow for future expansion using an external module.
NOTE
Startup and operational checks must be performed by an authorized Eaton
Customer Service Engineer, or the warranty terms specified on page W-1 become
void. This service is offered as part of the sales contract for the UPS. Contact an
Eaton service representative in advance (a minimum two-week notice is required)
to reserve a preferred startup date.