3.1.5 Engineering coordination
Attention should be paid to the following items before construction:
Power line specification.
The power line specification shall meet the requirements of maximum discharge
current for each product in table2-2.
Mounting space and bearing capacity.
Make sure that the battery has enough room to install, and that the battery rack and
bracket have enough load capacity.
Wiring.
Make sure the power line and ground wire are reasonable. Not easy to short-circuit,
water and corrosion.
3.2 Equipment installation
Table 3-2 Installation steps
Step1
Installation
preparation
Confirm that the ON/OFF switch on the front panel of each
B4874 unit is in the “OFF” state to ensure no live operation.
Step 2
Mechanical
installation
1. Cabinet placement position determination
2. Top cables pre-installed
3. Battery module installation
Step3
Electrical
installation
1. Battery module parallel cable installation
2. Battery module Power cable- positive installation
3. Battery module Power cable- negative installation
4. Communication parallel cable connection
Step4
Battery system
self-test
1. Press the ON/OFF switch to the "ON" state
2. BMS system power-on activation
3. Check the system output voltage
4. Shut down the system
Step5
Connect to the
inverter
1. Wiring the battery system Power cable- positive and
Power cable- positive to the circuit breaker between the
inverter and battery system.
2. Connect the Communication cable-to inverter2 to the
inverter
3.2.1 Installation preparation
1.
Prepare equipment and tools for installation
2.
Check the cabinet and confirm that the ON/OFF switch on the front panel of each battery
module is in the "OFF" state to ensure no live operation.
Communication
cable-to
inverter2
Black/L2000mm/
Double RJ45 plug
1
1
1
1