4. Refrigerator Installation and Commissioning
•
Make sure there is enough cable for the refrigerator to be moved for
maintenance and cleaning.
•
Ensure that the PV switch on the refrigerator is in the ‘OFF’ position.
•
Connect the cable to the refrigerator and turn the PV switch ‘ON’.
•
Very firmly secure the solar cable to the wall, ensuring that if it is pulled
it cannot strain the electrical connections.
•
Check the refrigerator compartment temperature display for operation.
Use a torch if natural light is insufficient.
•
Check the refrigerator cooling circuit is working (condensers should get
warm).
•
Allow the temperature to stabilise (this may take up to 7 days)
•
Check that the refrigerator compartment is +4
C to +6
C
5. F
inally…
STOP AND THINK
Have we done a good job?
Is it good quality?
•
Check that all cables are securely fixed and terminated
•
Complete the user training. Make sure the user understands:
How to get help,
How to operate the system,
How to do routine maintenance.
•
Tidy up the site making sure nothing is left behind.
•
Check that the installation record is complete and signed by the
responsible persons.
Signature of person responsible for installation ......................................................
Signature of person responsible for health centre ...................................................