4
ASSEMBLY
A. Erecting The Room
The steps in this section need to be completed each time the room is erected .
FIG. 1
Side Roof Pole
Central Roof
Pole
Arch Pole
Vertical Pole
STEP 1
Arch Pole
• Assemble the sectioned poles by snapping the sections
together .
• Insert the arch pole into the fabric .
STEP 2
Ball Joint
Side Roof Poles
• Insert the side roof poles into the fabric .
• Secure the side roof poles to the ball joints .
If the ball joint was not pre-installed on the camper, attach
it to the side wall below the top folding portion of the
camper, as indicated .
STEP 3
Arch Pole
Vertical Pole
• Insert the vertical poles into the fabric .
• Secure the vertical poles to the arch pole .
STEP 4
Ball Joint
Central
Roof Pole
Vertical
Pole
• Pull the vertical poles away from the camper and insert the
central roof pole into the fabric .
• Insert the central roof pole into the ball joint at the peak of
the folding wall .
STEP 5
Arch Pole
Central
Roof Pole
• Insert the central roof pole into the arch pole opening .
• Raise the Screen Room by moving the vertical poles into a
standing position .