When modules have been installed but the system has not 
been connected to the grid yet, each module string should 
be kept under open-circuit conditions and proper actions 
should be taken to avoid dust and moisture penetration 
inside the connectors. 

 

In case where a cable connection method not included in 
the  below  is  used,  please  confirm  the  suitable  cable 
length with DMEGC 

Solar’s sales representative

 

For different DMEGC Solar

’s

 module types, DMEGC Solar 

offers  optional  cable  lengths  to  match  various  system 
configurations. 

 

Recommended system cable schemes are shown below: 

1. Portrait two rows installation

 

 

Note:  Adjacent  two  modules  (up  and  down)  need  to  be 
rotated 180 degrees 

2. Portrait one row installation

 

 

3. Landscape installation

 

 

Note: Adjacent two modules (left to right) need to be 
rotated 180 degrees 

4. Leapfrog

 

 

The  maximum  distance  between  two  adjacent  module 
frames should be within 50 mm (1.96in) for the side with 
mounting clamps, and 25 mm (0.98in) for the side without 
mounting  clamps,  in  order  to  meet  the  system  cable 
scheme. 

Correct Connection Connectors 

 

Make  sure  that  all  connections  are  safe  and  properly 
mated. The PV connector should not be subject to stress 
from  the  exterior.  Connectors  should  only  be  used  to 
connect the circuit. They should never be used to turn the 
circuit on and off. 

 

Connectors  are  not  waterproof  when  unmated.  When 
installing  modules,  connector  should  be  connected  to 
each other as soon as possible or appropriate measures 
(like using connector endcaps) should be taken to avoid 
moisture and dust penetrating into the connector. 

 

Do not connect different connectors (manufacturer and 
type) together. 

 

Do  not  clean  or  precondition  the  connectors  using 
lubricants or any unauthorized chemical substances 

Use of Suitable Materials 

 

Only use dedicated solar cable and suitable connectors 
(wiring should be sheathed in a sunlight-resistant conduit 
or,  if  exposed,  should  itself  be  sunlight-  resistant)  that 
meet local fire, building and electrical regulations. Please 
ensure  that  all  wiring  is  in  perfect  electrical  and 
mechanical condition. 

 

Installers may only use cables listed and labeled as or PV 
wire, and the cable with a cross section area of at least 4 
mm²   (12  AWG),  90°C  wet  rated  in  other  areas  (i.e.  IEC 
62930 approved), with proper insulation which is able to 
withstand  the  maximum  possible  system  open-circuit 
voltage. 

 

Only copper conductor material should be used. Select a 
suitable conductor gauge to minimize voltage drop and 
ensure that the conductor ampacity complies with local 
regulations. 

Cable and Connector Protection 

 

Secure  the  cables  to  the  mounting  system  using  UV- 
resistant cable ties. Protect exposed cables from damage 
by  taking  appropriate  precautions  (e.g.  placing  them 
inside  a  metallic  raceway  like  EMT  conduit).  Avoid 
exposure to direct sunlight. 

 

A minimum bending radius of 60 mm (2.36 in) is required 
when  securing  the  junction  box  cables  to  the  racking 
system. 

 

Protect exposed connectors from weathering damage by 
taking appropriate precautions. Avoid exposure to direct 
sunlight. 

Summary of Contents for M10-54H

Page 1: ...an Group DMEGC Magnetics Co Ltd Hengdian Industrial Area Dongyang City Zhejiang Province China Tel 86 579 86310330 E mail solar dmegc com cn Ver 202206 Installation Manual of Standard Solar Modules Ph...

Page 2: ...fety Precautions 3 3 Mechanical Electrical Specifications 3 4 Unpacking and Storage 4 5 Module Installation 5 5 1 Module Wiring 6 5 2 Grounding 8 6 Mounting Instructions 8 6 1 Mounting Method Bolting...

Page 3: ...e module such as terminals can result in injury or death irrespective of whether or not the module and the other electrical equipment have been connected General Safety All modules must be installed b...

Page 4: ...onths and extra precautions should be taken to prevent connectors from being exposed to moisture or sunlight like using connector endcaps In any circumstance for pallets of modules packaged in landsca...

Page 5: ...open air climates as defined in IEC 60721 2 1 Classification of environmental conditions Part 2 1 Environmental conditions appearing in nature Temperature and humidity It is recommended that PV module...

Page 6: ...same cell cell row or module portion for extended and repeated periods of time e g more than 200 daylight hours over the warrantied service lifetime Power dissipated in fully or partially shaded cell...

Page 7: ...ctor should be connected to each other as soon as possible or appropriate measures like using connector endcaps should be taken to avoid moisture and dust penetrating into the connector Do not connect...

Page 8: ...es DMEGC Solar s Modules can be grounded using third party grounding devices so long as they are certified for grounding modules and the devices are installed according to the manufacturer s specified...

Page 9: ...figure 3 below figure 3 6 2 Mounting Method Clamping The mechanical load test with these mounting methods were performed according to IEC 61215 Top or bottom clamping methods will vary and are depende...

Page 10: ...re of 2400 Pa the modules are designed to meet a maximum positive pressure of 3600 Pa and negative pressure of 1600 Pa this design load was then tested with a safety factor of 1 5 times For bifacial d...

Page 11: ...ort frame Bolt installation Clamp installation Clamp position 0 H 1 4W Loading capacity Test load positive 5400Pa negative 2400Pa Design load positive 3600Pa negative 1600Pa Loading capacity Test load...

Page 12: ...ps at the long frame Clamp installation Clamp position 1 4L 50 S 1 4L 50 1 2L 80 S 1 2L 30 1 6L 50 H 1 6L 50 Loading capacity Test load positive 5400Pa negative 2400Pa Design load positive 3600Pa nega...

Page 13: ...bolts at the long frame inner holes 8 bolts at the long frame Bolt installation Loading capacity Test load positive 5400Pa negative 2400Pa Design load positive 3600Pa negative 1600Pa Test load positi...

Page 14: ...oved using a soft brush Periodically inspect the system to check the integrity of all wiring and supports To protect against electric shock or injury electrical or mechanical inspections and maintenan...

Page 15: ...asive to glass EPDM silicone aluminum or steel Conduct the cleaning activities avoiding the hottest hours of the day in order to avoid thermal stress on the module CLEANING METHODS Method A Compressed...

Page 16: ...DMEGC Solar PV Modules Installation Manual www dmegcsolar com 16 DMXXXM2 60SW BW BB DMXXXM2 G B72SW BW BB BT DMXXXM2 72SW BW BB DMXXXP1 60HSW BW DMXXXP1 72HSW BW DMXXXP1 60SW BW DMXXXP1 72SW BW...

Reviews: