2–14
DEC FDDIcontroller/EISA Installation
2.6 Verifying the Installation
Complete the following steps to verify that the controller(s) are
installed and operating properly in your computer:
1. Turn on power to the computer and observe the controller
LED(s).
2. Note the following events (within 10 seconds after the com-
puter power is turned on):
a. The controller LED on the mounting bracket flashes
green (three flashes) for approximately 1 second.
b. When the controller passes the powerup self-test, the
LED turns off.
A steady red LED indicates a powerup self-test failure.
NOTE
For the DAS model, the LED on each card indicates the
status of the card port, and a steady red indication on the
DAS daughter card indicates a possible failure with that
card.
If you observe any indication other than a successful self-test, turn
off power to the computer, reseat the installed controller card(s),
then repeat step 1.
If the self-test fails repeatedly, refer to Table 3-1 for problem solv-
ing information.
You are now ready to install your device driver:
•
To install device drivers from diskette 1, the DOS-format
distribution diskette, go to Section 2.7.
•
To install the SCO UNIX device driver, go to Section 2.8.