Check
List
Task
Topic
☐
11
Install the PIB.
See
Install the power interposer board
on
page 155.
☐
12
Install the power supply module or power
supply blank.
See
Install the cooling fan assembly
page 175.
☐
13
Install expansion card riser 2.
See
Install the expansion card risers
on
page 106.
☐
14
Install the air shroud, if applicable.
See the relevant topic, depending on
your system:
Install the non-GPU air shroud
on page
169
on page 171
☐
15
Install the system cover.
See
on page
173.
☐
16
Slide the system into the cabinet.
See
Slide the system into the cabinet
page 165.
☐
17
Connect the cable cords.
See
Connect the I/O cables and power
on page 164.
☐
18
Install the front bezel.
See
on page 166.
Perform mandatory software tasks to return the node to operation:
☐
19
Return the node to operation.
See "Return the node to operation" in
the VxFlex Ready Node Field Replacement
Unit Software Guide
.
Removing Power Interposer Board
The Power Interposer Board (PIB) connects the hot-swappable power supply units
(PSUs) to the system board.
Before you begin
Follow all safety guidelines.
CAUTION
When replacing the system board, disconnect the cables from the system board,
but do not disconnect the cables attached to the PIB.
CAUTION
To prevent damage to the power interposer board, you must remove the power
supply module (s) or power supply blank from the system before removing the
power interposer board or power distribution board.
Procedure
1. Disconnect the cables connected from the power interposer board (PIB) to the
system board, and remove the cables from the cable retention brackets.
Hardware FRU procedures
154
VxFlex Ready Node R840