Cabling Your Cluster Hardware
31
d
Connect a cable from Fibre Channel switch 0 (sw0) to the second
front-end fibre channel port on SP-B.
e
Connect a cable from Fibre Channel switch 1 (sw1) to the third front-
end fibre channel port on SP-A.
f
Connect a cable from Fibre Channel switch 1 (sw1) to the third front-
end fibre channel port on SP-B.
g
Connect a cable from Fibre Channel switch 1 (sw1) to the fourth
front-end fibre channel port on SP-A.
h
Connect a cable from Fibre Channel switch 1 (sw1) to the fourth
front-end fibre channel port on SP-B.
NOTE:
Additional cables can be connected from the fibre channel switches to the
storage system if there are available front-end fibre channel ports on the storage
processors.
Figure 2-11.
Cabling a SAN-Attached Cluster to the Dell/EMC CX4-480
01
01
2
3
01
01
2
3
01
2
3
01
2
3
cluster node 2
cluster node 1
CX4-480 storage system
0 1
0 1
HBA ports (2)
HBA ports (2)
SP-A
SP-B
sw0
sw1
Summary of Contents for CX4 Series
Page 5: ...Contents 5 A Troubleshooting 55 B Zoning Configuration Form 61 C Cluster Data Form 63 ...
Page 6: ...6 Contents ...
Page 38: ...38 Cabling Your Cluster Hardware ...
Page 54: ...54 Preparing Your Systems for Clustering ...
Page 62: ...62 Zoning Configuration Form ...
Page 68: ...68 Index ...