background image

Before starting work on the pump, make sure that the electricity 
supply has been switched off and that it cannot be accidentally 
switched on.

Correct earthing for all borehole pump installations is essential for 
safety and pump motor protection. Consult a licensed electrician for 
advice on requirements.

The electrical connection should be carried out by an authorised 
electrician in accordance with local regulations.

i)   General Information

WARNING

WARNING

WARNING

4

4.  ELECTRICAL CONNECTIONS

Ÿ

The rated maximum current, supply voltage and cosØ are given on a loose data 
plate supplied with the pumps which must be fitted close to the installation site.

Ÿ

The required voltage quality for DAYLIFF DS motors measured at the motor 
terminals  is  -10%/+10%  of  the  nominal  rated  voltage  during  continuous 
operation including variations in the supply voltage and cable losses.

Ÿ

 All motors must be fitted with a mains isolator and coarse current protection in 
the  form  of  an  MCB  or  fuse.  Coarse  current  rating  should  be  approx  3X 
maximum rated motor current.

Ÿ

For all three phase motors and single phase motors above 1.1kW a DOL starter 
is required. Note that starting current is between 4X and 6X the rated motor 
current which due to the low inertia of a submersible pump is reached in about 
0.1 seconds. DOL starting is therefore recommended for motor starting up to 
30kW  motor  sizes  as  the  total  system  load  is  less  than  with  a  Star  Delta 
alternative. For alternative starting arrangements options of a soft starter or auto 
transformer starter should be used.

Ÿ

It  is  essential  to  provide  motor  protection  from  high/low  current  conditions 
outside the limits of +10%, -10% of the rated full load running current, high 
current  protection  being  provided  by  a  DOL  starter  overload  relay.  Also 
recommended  for  3-phase  motors  is  protection  against  phase  loss,  phase 
asymmetry  and  high/low  voltage  variations  (<+10%,  >-10%)  of  nominal 
supply voltage which can be provided by a multi-function relay. 

Ÿ

Also generally recommended unless water availability is assured is low level 
protection to prevent the pump running dry. 

Summary of Contents for D3SP

Page 1: ...Installation Operating Manual DS DSP D3SP Submersible Borehole Pumps...

Page 2: ...otors Three Phase Motors 4 INSTALLATION Pump Application Pump Position Pump Lowering 5 PUMP OPERATION 6 MAINTENANCE 7 TROUBLE SHOOTING 8 WARRANTY 9 2 DELIVERY STORAGE Delivery Storage Handling 1 1 2 2...

Page 3: ...sheet which will be supplied with the pump DAYLIFF D3SP pumps are compact 3 diameter submersible multistage centrifugal pumps specifically designed for small scale water supplies from boreholes and we...

Page 4: ...ii Motor All pumps are fitted with sealed liquid cooled oil filled 2 pole asynchronous squirrel cage motors constructed principally of stainless steel Single phase motors require purpose designed con...

Page 5: ...t Leakage at this joint will cause motor failure Care must be taken when fitting the motor tail cable to the motor The connection between the tail cable and the motor should be lubricated with a non c...

Page 6: ...in the form of an MCB or fuse Coarse current rating should be approx 3X maximum rated motor current For all three phase motors and single phase motors above 1 1kW a DOL starter is required Note that...

Page 7: ...entification of the start run and common windings is essential or else the motor will burn out Extra care must therefore be taken when connecting and if in doubt the pump supplier should be consulted...

Page 8: ...and 35m for D3SP Pumped liquid should be clean thin and non explosive containing no solid 3 particles or fibres Sand content should not exceed 50gm m or else pump life will be reduced and any warrant...

Page 9: ...ecommended that the complete pump is submerged at least 3m the dynamic water level and if possible the pump should be installed at least 3m from the bottom of the borehole to prevent silting damage As...

Page 10: ...o approximately 1 3 of its maximum volume of water Observe if there are impurities in the water and then gradually open the valve until the water is observed to be clear If the water continues to be s...

Page 11: ...e Fault Finding Guide Also important is a periodic check of motor winding and insulating resistance especially if there is an abnormal operating current or voltage reading For three phase motors windi...

Page 12: ...al call service technician Motor starter contactor defective Repair the motor starter contactor The control circuit has been interrupted or is defective Check the electric installation No electricity...

Page 13: ...the strainer Replace or repair the pump The valves in the discharge pipes are partly closed or blocked Check and clean or replace the valves and discharge pipe Wrong direction of rotation Change direc...

Page 14: ...lve changed Pull out the pump and clean or replace the non return valve The non return valve is leaking or stuck half open Long period until water flow after start Increase the installation depth of t...