vi
GUIDE TO INSTALLATION
The following can be used as a checklist to verify all the steps necessary to complete
installation of the PWR power Supply.
CAUTION
Before wiring the device make sure the power is disconnected to avoid
electrical shock.
1) Read all information in the section “Safety Precautions” at the beginning of this manual.
2) Mount the PWR near the Reading Station.
3) With AC line voltage OFF, wire the AC Line input to the PWR AC Terminal Block see
par. 1.2.1.
4) System
Wiring:
Directly to Scanners
Provide correct and complete system cabling to the PWR according to the signals
necessary for the layout of your application. (See par. 1.2.2 and your scanner manual
for details. All system cables must pass through the glands.
With SC8000
Connect the SC8000 Controller to the PWR by means of the appropriate cables (see
par. 1.2.3 and the SC8000 manual for details). All cables must pass through the glands.
5) Close and lock the PWR enclosure.
6) Apply the AC line voltage from the building installation and check that the PWR powers
up correctly.
The installation is now complete.