background image

10

2.0 PIPING

2.1  Split Air Cooled Unit Piping

Refer to the attached Line Sizing chart on page 31 for a guideline for sizing refrigerant lines.  The 
ultimate responsibility for line size selection is that of the installing contractor or project engineer.  
Data Aire does not assume this responsibility.  The chart covers distances up to 200 equivalent feet.  
For installations beyond this distance, consult  ASHRAE or similar references.

Standard Piping practice must be used to ensure proper oil return and effi cient operation.  
The interconnecting lines to the remote air cooled condenser must be installed by a 
qualifi ed refrigeration mechanic.

2.1.1 Discharge 

Lines

Discharge lines, also called Hot Gas lines, should be trapped at the top (inverted) and bottom, as well 
as every 20 feet of vertical rise.  Discharge line check valves are recommended on all installations, 
especially those where there are long pipe runs or cold climate.  Check valves should be installed 
six feet from the compressor.

Discharge line pressure drop should not exceed 6 PSI.  Recommended gas velocity for proper oil 
return is 1,000 FPM.  Slope horizontal lines downward in the direction of refrigerant fl ow 1/2” for 
every ten feet of line length.

2.1.2 Liquid 

Lines

Liquid line size is determined by pressure drop and velocity.  The liquid line pressure drop should be 
not exceed 5 PSI.  The recommended velocity should be between 200 and 300 FPM. 
To avoid excessive liquid line pressure drop, the air cooled condenser should be located above or at 
the same level as the evaporator.  Condenser installation more than ten feet below the evaporator 
should be avoided.

2.1.3 Suction 

Lines

Some applications call for the compressor to be mounted in the outdoor condenser, or condensing 
unit.  Such cases require fi eld piping of liquid and suction lines.  Suction lines are trapped similarly 
to discharge lines except for the inverted trap at the top of the suction line and the line needs to be 
insulated with a minimum 1/2” thick insulation or per code.  Common practice for suction line selection, 
see page 

31

, and installation should be followed.

2.1.4  Connection Sizes, Air Cooled Units

Model Hot 

Gas 

Liquid 

Suction

DAMA 0112 

1/2” 

1/2” 

3/4” 

Note:  Unit will have a Liquid Line and

DAMA 1.512 

1/2” 

1/2” 

3/4” 

either a Hot Gas or Suction Line 

DAMA 

0212 

1/2” 1/2” 3/4”

DAMA 

2.512 

1/2” 1/2” 3/4”

Field connections at the indoor evaporator and remote condenser or condensing unit will 
not necessarily be the same as the fi eld pipe size required.  In some cases these will 

Summary of Contents for MINI CEILING SERIES

Page 1: ...MINI CEILING SERIES Installation Operation and Maintenance Manual 1 1 5 2 and 2 5 ton Air Water and Glycol Cooled DX and Chilled Water...

Page 2: ...ce to Data Aire units should be done by qualified individuals with an adequate background in areas such as HVAC electrical plumbing and electronics as applicable Service performed by unauthorized or u...

Page 3: ...2 Water Glycol Cooled Unit Piping 12 2 2 1 Connection Sizes Water Glycol Cooled Units 13 2 2 2 Connection Sizes Fluid Coolers 13 2 3 Auxiliary Chilled Water Coil Piping 13 2 4 Condensate Drain Piping...

Page 4: ...s 22 5 3 Refrigerant Handling 22 5 4 Important Refrigeration Component 23 5 4 1 Expansion Valve 23 5 4 2 High Pressure Cutout Switch 23 5 4 3 Low Pressure Cutout Switch 23 6 0 GLYCOL SYSTEMS 24 6 1 Gl...

Page 5: ...TY 29 10 0 CONTACT DATA AIRE 30 LINE SIZING CHART 31 Monthly Maintenance Inspection Checklist 32 Quarterly Maintenance Inspection Checklist 33 Superheat and Suction Pressure Troubleshooting Guide 34 T...

Page 6: ...conditions and to prevent the CRAC units from running excessively to maintain the room s conditions 1 2 Inspection This Data Aire unit has been factory run tested and has gone through a comprehensive...

Page 7: ...il Four threaded support rods must be securely attached to the building structure Raise the evaporator section with an appropriate lifting device Attach washers nuts and jam nuts to each threaded rod...

Page 8: ...led condensing sections have no airflow connections Typical installations have the condenser or condensing section physically near the evaporator especially since most have shared electrical line powe...

Page 9: ...s forming a weak acid and over time can cause pin hole leaks to develop in the coil tubes When equipment is installed after storage caution should be taken to inspect and replace if required rubber ho...

Page 10: ...of refrigerant flow 1 2 for every ten feet of line length 2 1 2 Liquid Lines Liquid line size is determined by pressure drop and velocity The liquid line pressure drop should be not exceed 5 PSI The...

Page 11: ...11 2 1 5 Field Piping Remote Condenser 2 1 6 Field Piping Remote Condensing Unit...

Page 12: ...clearance problem Shutoff valves field provided should be installed within a few feet of the inlet and outlet connections of the CRAC unit to allow the unit to be isolated for service There should be...

Page 13: ...have the 5 plenum below the evaporator drain pan with knockouts that allow field supplied and installed condensate lines to be routed out either side of the unit A union is recommended at the field co...

Page 14: ...034kPa by using dry nitrogen with a trace of refrigerant Check the entire system for leaks with suitable leak finder per local code including but not limited to all braze joints caps and fittings and...

Page 15: ...inimum Circuit Ampacity also known as Wire Sizing Amps will dictate the minimum required wire gage Maximum Overcurrent Protection Device amps will dictate the maximum circuit breaker or fuse size 3 3...

Page 16: ...be field accessed on terminals 11 common and 12 normally closed or 13 normally open of terminal block TB1 This is a normally open or normally closed dry contact will reverse position upon alarm and i...

Page 17: ...be unbolted from their collapsed shipping position and extended prior to placing the unit on its pad Each leg extends down approximately 18 and reattaches using the same bolts the bolts are placed th...

Page 18: ...or Mounting a condenser or condensing unit more than ten feet below the evaporator is not recommended Excessive liquid line pressure drop can cause poor evaporator performance 4 6 Fluid Coolers Model...

Page 19: ...charging should be done by referring to the unit electrical nameplate for the factory charge Although this figure represents the original factory charge it is still necessary to measure and note prope...

Page 20: ...a compressor if the system has a refrigerant holding charge the crankcase heatershouldbeenergizedforaminimumof12hourstoreducethepossibilityofliquidslugging on start up Failure to energize the crankcas...

Page 21: ...pressure drop low subcooling or low charge It is likely that more refrigerant will be required to complete the charging procedure Adjust the refrigerant charge until the sight glass clears or has onl...

Page 22: ...head pressure sensing transducer is connected to a shrader fitting on the discharge line and water is regulated into the condenser coil Condenser coils may be plate fin or coaxial type Before startin...

Page 23: ...g Any field adjustment should be to fine tune a system that has stabilized and already has acceptable operating parameters 5 4 2 High Pressure Cutout Switch Each refrigerant circuit is protected by a...

Page 24: ...freeze protection 6 2 Internal Fluid Volume Evaporator Without With Internal Volume Energy Saver Coil Energy Saver Coil Model Volume Gallons Volume Gallons DAMG 0112 0 5 2 0 DAMG 1 512 0 5 2 0 DAMG 02...

Page 25: ...ed to complete a thorough unit installation Start up is not complete until the Mini DAP II control panel settings are established 7 4 Optional Mini DAP III Microprocessor Control Panel The Mini DAP II...

Page 26: ...dary heat exchanger The internal wiring of the heat exchanger is found on a separate diagram which can be found on the inside cover of the heat exchanger electrical box Both diagram types are also pla...

Page 27: ...y to ensure proper tension If tightening is required loosen the four motor mounting bolts Turn the adjustment screw on the end of the motor mounting channel until the proper belt tension is attained R...

Page 28: ...led refrigerant filter driers do not normally require maintenance When replacing compressors or other repairs that open the refrigeration system to atmosphere it is advisable to replace the filter dri...

Page 29: ...uipment goods or merchandise arising out of any defect in or failure of any equipment of its manufacture and Buyer hereby waives any claim against Seller arising out of such claim This warranty shall...

Page 30: ...e com Technical Support engineering dataaire com Engineering sales dataaire com Sales Web site www dataaire com Job Information Data Aire Job Number ________________________________________ Evaporator...

Page 31: ...5 8 7 8 7 8 7 8 5 5 1 2 5 8 5 8 5 8 26 13 7 8 7 8 7 8 7 8 6 6 1 2 5 8 5 8 5 8 30 15 7 8 7 8 7 8 7 8 8 8 5 8 7 8 7 8 7 8 10 10 5 8 7 8 7 8 7 8 13 13 7 8 7 8 7 8 7 8 SUCTION LINES SINGLE CIRCUIT SYSTEMS...

Page 32: ...mp operation ___ Auto air vent clean of mineral deposits Condensate Drain and Pump if applicable ___ Check for water leaks ___ Check for restricted air flow ___ Pump operation Steam Generating Humidif...

Page 33: ...ng valve function ____ Check solution _____ ____ Check for water glycol leaks piping area ____ Water Glycol flow switch operational Glycol Pump s ____ Glycol leaks pump area ____ Pump operation ____ A...

Page 34: ...across valve a Same as 11 above b Undersized distributor nozzle or circuits c Low condensing temperature High Suction Pressure Low Superheat 1 Oversized valve 2 TEV seat leak 3 Low superheat adjustmen...

Page 35: ...0 8 73 8 49 82 4 R 22 R 407C Temperature Pressure PSI Pressure PSI 50 84 1 77 1 55 92 6 106 0 60 101 6 116 0 65 111 3 127 0 70 121 5 139 0 75 132 2 151 0 80 143 7 163 0 85 155 7 177 0 90 168 4 191 0 9...

Page 36: ...eat Elements 28 High Pressure Cutout Switch 23 Horizontal Units 8 Humidifier Canister 27 A Air Cooled Systems 7 8 10 20 Air Filters 27 Air Vents 12 Ambient Thermostats 18 Auxiliary Wiring 15 B Bearing...

Page 37: ...nued Dry Steam Humidifier Steam Generator Humidifier 14 I Inspection 6 Installation 6 Internal Volume see Volume L Liquid Lines 10 11 31 Leak Testing 14 Locating Evaporator 6 Secondary Heat Exchanger...

Page 38: ..._____ _____________________________________________________________________________________________ _____________________________________________________________________________________________ ______...

Page 39: ...3 www dataaire com e mail sales dataaire com A Member of the CS Group of Companies 2009 Data Aire Inc Data Aire Inc reserves the right to make design changes for the purpose of product improvement or...

Reviews: