1 - Introduction

These instructions pertain to the Maneurop® MT, 

MTZ  &  NTZ  compressors  used  for  refrigeration 

systems. They provide necessary information re-

garding safety and proper usage of this product.

2 – Handling and storage 

  •   Handle  the  compressor  with  care.  Use  the 

dedicated  handles  in  the  packaging.  Use  the 

compressor lifting lug and use appropriate and 

safe lifting equipment.

  •   Store  and  transport  the  compressor  in  an 

upright position.

  •   Store  the  compressor  between  -35°C  and 

50°C.

  •   Don’t  expose  the  compressor  and  the  packa

-

ging to rain or corrosive atmosphere.

3 – Safety measures before assembly

 Never use the compressor in a flammable at-

mosphere.

  •   The compressor ambient temperature may not 

exceed 50°C during off-cycle.

  •   Mount the compressor on a horizontal flat sur

-

face with less than 3° slope.

  •   Verify that the power supply corresponds to 

the  compressor  motor  characteristics  (see 

nameplate).

  •   When  installing  MTZ  or  NTZ,  use  equipment 

specifically reserved for HFC refrigerants which 

was never used for CFC refrigerants.

  •   Use clean and dehydrated refrigeration-grade 

copper tubes and silver alloy brazing material.

  •   Use clean and dehydrated system components.

  •   The piping connected to the compressor must be 

flexible in 3 dimensions to dampen vibrations.

4 - Assembly

  •   Slowly  release  the  nitrogen  holding  charge 

through the schrader port.

  •   Remove  the  gaskets  when  brazing  rotolock 

connectors.

  •   Always use new gaskets for assembly.

  •   Connect the compressor to the system as soon 

as  possible  to  avoid  oil  contamination  from 

ambient moisture.

  •   Avoid material entering into the system while 

cutting  tubes.  Never  drill  holes  where  burrs 

cannot be removed.

  •   Braze  with  great  care  using  state-of-the-art 

technique  and  vent  piping  with  nitrogen  gas 

flow.

  •   Connect  the  required  safety  and  control  de

-

vices. When the schrader port is used for this, 

remove the internal valve.

5 – Leak detection

 Never pressurize the circuit with oxygen or dry 

air. This could cause fire or explosion.

  •   Do not use dye for leak detection.

  •   Perform a leak detection test on the complete 

system.

  •   The low side test pressure must not exceed 25 

bar.

  •   When a leak is discovered, repair the leak and 

repeat the leak detection.

6 – Vacuum dehydration

  •   Never  use  the  compressor  to  evacuate  the 

system.

  •   Connect a vacuum pump to both the LP & HP 

sides.

  •   Evacuate the system to a pressure of 500 µm 

Hg (0.67 mbar) absolute.

  •   Do not use a megohmmeter nor apply power 

to the compressor while it is under vacuum as 

this may cause internal damage.

7 – Electrical connections

  •   Switch off and isolate the main power supply. 

See overleaf for wiring details.

  •   The  compressor  is  protected  against  excess 

current  and  temperature  by  an  internal  over-

load protector. Follow local regulations regar-

ding  power  line  protection.  The  compressor 

must be connected to earth.

  •   All electrical components must be selected as per 

local standards and compressor requirements.

8 – Filling the system

  •   Keep the compressor switched off.

  •   Fill  the  refrigerant  in  liquid  phase  into  the 

condenser or liquid receiver. The charge must 

be as close as possible to the nominal system 

charge to avoid low pressure operation and ex-

cessive superheat.

  •   Keep the refrigerant charge below 2.5 kg per 

compressor  cylinder  if  possible.  Above  this 

limit;  protect  the  compressor  against  liquid 

flood-back with a pump-down cycle or suction 

line accumulator.

  •   Never  leave  the  filling  cylinder  connected  to 

the circuit to avoid overfilling.

9 – Verification before commissioning

  Use  safety  devices  such  as  safety  pressure 

switch and mechanical relief valve in compliance 

with both generally and locally applicable regu-

lations and safety standards. Ensure that they are 

operational and properly set. 

  Check that the settings of high-pressure swit-

ches and relief valves don’t exceed the maximum 

service pressure of any system component.

  •   A  low-pressure  switch  is  recommended  to 

avoid vacuum operation. Minimum setting 0.1 

bar.

  •   Verify  that  all  electrical  connections  are  pro

-

perly  fastened  and  in  compliance  with  local 

regulations.

  •   When a crankcase heater is required, it must be 

energized at least 12 hours before initial start-

up and start-up after prolonged shutdown.

10 – Start-up

  •   All  service  valves  must  be  in  the  open  posi

-

tion.

  •   Balance the HP/LP pressure.

  •   Energize the compressor. It must start promptly. 

If it does not, switch it off immediately. Possible 

single  phase  miswiring  can  cause  burn-out 

within seconds.

  •   If the compressor does not start, check wiring 

conformity and voltage on terminals.

  •   If  the  internal  overload  protector  trips  out,  it 

must  cool  down  to  60°C  to  reset.  Depending 

on ambient temperature, this may take up to 

several hours.

11 – Check with running compressor

  •   Check current draw and voltage.

  •   Check  suction  superheat  to  reduce  risk  of 

slugging.

  •   When a sight glass is provided observe the oil 

level at start and during operation to confirm 

that the oil level remains visible.

  •   Respect the operating limits as printed overleaf.

  •   Check all tubes for abnormal vibration. Move

-

ments  in  excess  of  1.5  mm  require  corrective 

measures such as tube brackets.

  •   When  needed,  additional  refrigerant  in  the 

liquid phase may be added in the low-pressure 

side  as  far  as  possible  from  the  compressor. 

The compressor must be operating during this 

process.

  •   Do not overcharge the system.

  •   Never release refrigerant to the atmosphere.

  •   Before  leaving  the  installation  site,  carry  out 

a  general  installation  inspection  regarding 

cleanliness, noise and leak detection.

  •   Record type and amount of refrigerant charge 

as well as operating conditions as a reference 

for future inspections.

12 - Maintenance

  Internal  pressure  and  surface  temperature 

are dangerous and may cause permanent injury.

Maintenance  operators  and  installers  require 

appropriate skills and tools. Tubing temperature 

may exceed 100°C and can cause severe burns.

  Ensure  that  periodic  service  inspections  to 

ensure system reliability and as required by local 

regulations are performed.

To  prevent  system  related  compressor  problems, 

following periodic maintenance is recommended:

  •   Verify that safety devices are operational and 

properly set.

  •   Ensure that the system is leak tight.

  •   Check the compressor current draw.

  •   Confirm that the system is operating in a way 

consistent with previous maintenance records 

and ambient conditions.

  •   Check  that  all  electrical  connections  are  still 

adequately fastened.

  •   Keep the compressor clean and verify the ab

-

sence of rust and oxidation on the compressor 

shell, tubes and electrical connections.

13 - Warranty

Always  transmit  the  model  number  and  serial 

number with any claim filed regarding this pro-

duct.

The  product  warranty  may  be  void  in  following 

cases:

  •   Absence of nameplate.

  •   External  modifications;  in  particular,  drilling, 

welding, broken feet and shock marks.

  •   Compressor opened or returned unsealed.

  •   Rust,  water  or  leak  detection  dye  inside  the 

compressor.

  •   Use of a refrigerant or lubricant not approved 

by Danfoss.

  •   Any deviation from recommended instructions 

pertaining to installation, application or main-

tenance.

  •   Use in mobile applications.

  •   Use in explosive atmospheric environment.

  •   No model number or serial number transmitted 

with the warranty claim.

14 – Disposal

Danfoss  recommends  that  compressors 

and compressor oil should be recycled by 

a suitable company.