Refrigerant charging
Installation checks
Oil charge and oil level
For the initial charge, the compressor
must not run and service valves must
be closed. Charge refrigerant as close
as possible to the nominal system
charge before starting the compres-
sor. Then slowly add refrigerant on
the low pressure side as far away as
possible from the compressor suction
connection. The refrigerant charge
quantity must be suitable for both
winter and summer operation. R404A
The oil charge must be checked before
commissioning (1/4 to 3/4 of the oil
sight glass). Check the oil level again
after a minimum of 2 hours operation
at nominal conditions. In most instal-
lations the initial compressor oil char-
ge will be sufficient. In installations
with line runs exceeding 20 m or with
many oil traps or an oil separator, ad-
ditional oil may be required. Normally
the quantity of oil added should be no
more than 2% of the total refrigerant
charge. This percentage does not take
After a few running hours the main
system parameters shall be verified
to ensure that the system is working
correctly or eventually to adjust the
settings.
●
The evaporating temperature and
condensing temperature shall be com-
pared with the design conditions.
●
The superheat at the evaporator out-
let must be adjusted to optimise the
evaporator performance. Generally a
value of 5 to 6 K is recommended.
●
The compressor suction tempera-
ture gives information about the suc-
tion gas superheat at the compressor.
NTZ compressors can be operated at
a maximum suction gas temperature
of 20°C. However it is recommended
to keep the suction gas superheat at a
lower value to increase the compres-
sor performance and service life. On
the other hand, note that extremely
low superheat values can increase the
risk of unwanted liquid floodback to
is a near-azeotropic mixture and must
be charged in the liquid phase. R507A
is an azeotropic mixture and can be
charged either in liquid or gas phase.
Warning:
When a liquid line solenoid valve is
used, the vacuum in the low pressure
side must be broken before applying
power to the system.
into account oil contained in accesso-
ries such as oil separators or oil traps.
If this amount has already been added
and the oil level in the compressor
keeps decreasing, the oil return in the
installation is insufficient. Refer to sec-
tion "Piping design". In installations
where slow oil return is likely such as
in multiple evaporator or multiple con-
denser installations an oil separator is
recommended. Always use Danfoss
160Z lubricant for systems with NTZ
compressors and R404A or R507A.
the compressor. When a too high su-
perheat is noted while the expansion
valve setting is correct, the suction line
insulation between evaporator and
compressor should be checked and
eventually replaced by a higher qua-
lity insulation.
●
A too high discharge gas tempe-
rature can indicate a malfunctioning
condenser, presence of non-conden-
sable gasses, too high suction gas
superheat, refrigerant overcharging,
etc... The maximum allowable dischar-
ge line temperature as measured with
a temperature probe directly after the
compressor discharge connection is
115°C.
●
Power and current consumption
shall be compared with the table va-
lues at measured evaporating and
condensing temperature.
●
When after commisioning the liquid
sight glass indicates moisture, the filter
drier must immediately be replaced.