Erect all frames and put the purlins on the roof as the first section.
⚫
Use bolt M12x70 to fix the leg NO.5 and Roof beam NO.1 and Top connection
through NO.31
⚫
Use bolt M12x120 to fix the (NO.2,5) and Gable Purlin (NO.6,7).
⚫
Use bolt M12x100 to fix Tie down on the NO.2 and NO.5.
2.
’Roof Cover and Sidewalls’ Assembling Guide
⚫
Roof
-
Cover
⚫
Unpack the Roof
-
Cover and put onto a protecting foil or carpet to avoid it
getting dirty or damaged.
⚫
Throw 2 PCS of Setup
-
Ropes over the first unit of the tent.
⚫
Tie the Setup
-
Ropes with the straps inside of the Roof
-
Cover.
⚫
Lift the Roof
-
Cover up to the eaves and insert the Keder into the groves of the
Roof
-
Beams.
⚫
Slowly pull in the Roof
-
Cover with equal force on both sides.
⚫
Pull in until the Roof
-
Cover reaches the opposite eaves.
⚫
Repeat the procedure until all Roof
-
Covers have been pulled on.
Summary of Contents for PRO EventZone 9m Series
Page 1: ...for Storage PRO EventZone 9m Series Manual 25 06 2021...
Page 3: ......
Page 4: ......
Page 5: ......
Page 7: ......
Page 8: ...NO 11 Portal beams is on four corners for support Use bolt M12x70 to fix it...
Page 16: ...38 Sheaved block 1 wheel 2 2 2 2 39 Sheaved block 2 wheels 2 2 2 2 40 Bottom bardoor 4 4 4 4...
Page 17: ......