Shot Clock Installation Quick Guide
Page 2 of 2
DD5071871
Rev 00
31 May 2022
201 Daktronics Drive
Brookings, SD 57006-5128
www.daktronics.com/support
800.325.8766
Power
Only qualified individuals should complete the electrical installation; untrained personnel should not attempt
to install these displays or any of the electrical components. Improper installation can seriously damage the
equipment and be hazardous to personnel.
Shot clocks feature an 11' long 120 VAC power cord with a three-prong plug. Install a grounded receptacle
nearby so that the power cord can easily reach it. If the provided power cord does not reach a grounded
receptacle, it must be re-terminated with a longer cord.
Wired Signal
Wired signal installation requires routing control
cable from the control console to a signal junction
box (J-box) near the display. Refer to
typical signal layout. At a minimum, use a paired,
22 AWG shielded cable (Daktronics part # W-1077).
1.
Connect the cable to a dual 1/4" J-box at the
control console end.
2.
Route the cable in conduit from the J-box on
the control console end to a J-box near the shot
clock.
3.
Install the 1/4" phone plug (part # 0L-40683)
to the shot clock end of the cable. Be sure to
connect the cable shielding only in the J-box
on this end. DO NOT connect cable shielding at
the J-box near the control console.
4.
Insert the plug into the
J31 – SIGNAL IN
jack
located on the side of the shot clock.
5.
Connect a signal cable from the J-box on the
control console end to the
J1
,
J2
, or
J3
jack on
the rear of the All Sport 5000 console.
6.
Connect the Shot Clock Start/Stop Switch (0A-
1196-0031) to the
J7
jack on the rear of the All
Sport 5000 console.
Wireless Radio
A wireless radio system requires a radio receiver
mounted inside the shot clock. For more information,
refer to the
Gen VI Radio Installation Manual
(DD2362277)
, provided with the receiver and
available online at
.
Radio Settings
By default, radio receivers are set to Broadcast 1
("b1") and Channel 01 ("C1"). This may or may not
match the settings used by existing scoreboards in
the facility. Power ON the All Sport 5000 console to
check the radio settings as shown at right.
J1, J2,
or J3
All Sport Controller
J-Box:
Dual 1/4" Phone
(0A-1196-0013)
Pin
Color Function
tip
red
ring
black signal -
J-Box:
(Not provided by
Daktronics)
Signal Cable:
1 Pair, 22 AWG
(W-1077)
in Conduit
Signal Cable:
1/4" Male Phone to Pigtail, 10'
(0L-40683)
[To Main
Scoreboard]
Signal Cable:
10' (W-1340) 30' (W-1238)
20' (W-1236) 50' (W-1237)
Figure 4:
Shot Clock Wired Installation Diagram
Radio Receiver Antenna -
Facing Control Location
All Sport
Controller
with Radio
Option
Up to 500' away with
direct line of sight
Figure 5:
Shot Clock Wireless Installation Diagram
RADIO SETTINGS
BCAST 1 CHAN 01
All Sport Radio Settings
If the shot clock radio receiver settings DO NOT need to be changed, skip ahead to
Receiver Mounting
.
If the shot clock radio receiver Broadcast/Channel settings DO need to be changed:
1.
Disconnect power to the shot clock and use a Phillips
screwdriver open the front face panel.
2.
Use a Phillips screwdriver to remove the four screws
securing the radio receiver cover.
3.
Use a small flathead screwdriver to change the BCAST
and CHAN switches accordingly. Refer to
.
Note:
Do NOT change the FUNC switch; this must
always be set to "1".
4.
Replace the radio receiver cover.
5.
Proceed to
Step 2
of
Receiver Mounting
.
Receiver Mounting
1.
Disconnect power to the shot clock and use a Phillips screwdriver to open the front face panel.
2.
Use the double-sided adhesive tape to secure the radio receiver inside the bottom of the shot clock cabinet.
. Mount the radio receiver toward the side of the court where the controller is located.
3.
Connect the 6-pin cable from the radio receiver to the mating 6-pin
J21
jack on the LED driver.
Note:
The BB-2114 shot clock will include a 5-pin to 6-pin adapter connected to the 5-pin
J45
jack on a wiring
harness coming from the LED driver. Connect the 6-pin cable from the radio receiver to this adapter.
6-Pin Cable
Connection (J21)
6-Pin Cable
Connection (J45)
BB-2115
BB-2114
Radio Receiver
& Antenna
Mounting Locations
Radio Receiver
& Antenna
Mounting Locations
Figure 7:
Shot Clock Radio Mounting
4.
Mount the antenna as described below and illustrated in
:
a.
Route the antenna cable through the D hole on the lower side
of the shot clock cabinet. Again, the antenna should be on
the side that faces the control location for best reception.
b.
On the outside of the shot clock cabinet, attach the lock
washer, nut, and antenna.
c.
Attach the two small U-bolts around the antenna. This is for added protection from ball impacts.
5.
Ensure all internal wires are out of the way of getting pinched, and then close and secure the front panel.
6.
Power up the shot clock and All Sport 5000 console to test the radio control.
Light Strips
For installations with backboard light strips, refer to the
LTS-BB Backboard LED Light Strips Manual (DD4692853)
,
provided with the light strip kit and available online at
2.4GHZ
LL-2567
REV 01
POWER
RADIO IN RANGE
DATA OUT
DAKTRONICS
WIRELESS RECEIVER
FUNC
CHAN
BCAST
X1
X2
J4
0
0
0
1
1
1
Broadcast
Channel
Figure 6:
Radio Receiver with and without Cover
Gold Antenna
Connector
Shot Clock
Side Panel
Gold Washer
~3/4"
Gold
Nut
1/4" Black Nut
@4
U-bolt
@2
Antenna
1/4" Nut
@4
Figure 8:
Shot Clock Radio Antenna