SK2019 EU FDHD-V/P-AC-001
Location
Before installing and running the unit, please check the following:
1.
There must be enough space for unit installation and maintenance. Please refer to below figure for the unit's outlines
and dimensions and for the minimum distance between the unit and the obstacle/ any obstructions/ its surroundings.
2.
Please ensure there is enough space for piping connections and electrical wiring.
3.
Check whether the hanging rods can support the weight of the unit (see specification table for weight of the unit).
4.
The unit must be installed horizontally to ensure proper operation and condensate draining.
5.
The external static pressure of the ducting must be within the unit’s static press
ure range.
6.
Confirm that the unit has been switched OFF before installing or servicing the unit.
B
>200mm
-
>600mm
_
CEILLING
DRAIN PIPE
Installation Procedures
1.
The unit is designed to be installed in a concealed ceiling. Installation and maintenance should be performed by
qualified personnel who are familiar with local codes and regulations, and are experienced with this type of appliance.
2.
Please refer to the pictures below for installation procedures.
Counternut
Washer
NUT
Rod
Nut