10.3.2. ELC luminaires not installed: 

 

If after connecting ELC series luminaires it is observed that they  are not installed on 

the device, review the following points: 

 

 

The circuits must be configured in “

ELC

” mode

 

 

 

The device’s communication is only possible with Daisalux ELC series 24v luminaires.

 

 

 Communication  with  new  luminaires  connected  to  the  device  can  take  up  to  60 

minutes to establish from when they are connected to the device. 

 

 If  the  luminaires  have  been  previously  connected  to  another  device,  they  must 

remain  connected  and  with  power  for  24  hours  to  the  new  device  so  that  they  are 
installed on it. 

 

 The  distance  from  the  device  to  the  first  luminaire  on  the  circuit  and  between 

luminaires  on  the  same  circuit  must  not  exceed  80  metres.  At  greater  distances, 
correct communication of luminaires with the device is not guaranteed. 

 

 Check that the luminaires have power on their terminals. Check wiring on the circuit if 

there is no voltage on its input. 

 

  

If there is input voltage,  check that the light  or one  of the light’s signalling LEDs is 

illuminated or flashing. Otherwise, check the connection to the lu

minaire’s terminals 

or between the anchor plate and the luminaire.  

 

10.4. Battery Problems: 

10.4.1. Battery duration fault: 

When the device notifies a duration fault, check the following: 

 

Device’s  output  power  (must  be  within  the  ranges  described  in  this 

manual).  If  the 

power is excessive it is outside of specifications and therefore its duration is reduced 
to below that configured. 

 

If the power is within range, the battery will probably have to be replaced with a new 

one. 

10.4.2. Reversed battery connection: 

If there is a reversed battery connected, the fuses must be replaced after disconnecting 
the  battery.  After  replacing  the  fuses,  reconnect  the  battery  according  to  the  polarity 
indicated. 

 
 

11. Accessories 

11.1 LPSLan/LPSWeb/ModBus 

 

LPSLan is an accessory that adds ethernet connectivity to LPS24 devices. It includes a web 
server (LPSWeb) used to configure and display the status of centralised LPS series Daisalux 
through a local or internet network.  The system includes 

ModBus

 gateway for managing 

the LPS24 equipment. See connection information in 

6.3.7 LPSLan

 

 
It can accessed from a web browser so there is no need to install any additional software on 
your computer, tablet or smartphone. The only requirement is that you have a web browser 
and a network connection with the LPS series device. 
 
From  the  LPSWeb  the  device  status  can  be  viewed  and  certain  aspects  of  its  operation 
configured, as well as the centralised luminaires on the Daisalux ELC series connected to it. 
 
For a detailed description of the operating mode, consult the 

LPSWeb

 manual. 

 

Summary of Contents for LPS24

Page 1: ...V20200515 F8 LPS24 USER MANUAL Centralised emergency lighting device...

Page 2: ...V20200515 F8...

Page 3: ...S24 device 14 6 3 3 2 Remote fault connection to several LPS24 devices 15 6 3 4 Dry contacts CLP1 CLP4 15 6 3 5 Input 0 10V 17 6 3 6 Remote control TELEM 17 6 3 7 LPSLan 18 7 Switching on the LPS cent...

Page 4: ...roubleshooting 35 10 1 Output problems 35 10 1 1 Short circuit on the outputs 35 10 1 2 Over consumption in the outputs 35 10 1 3 Electronic fault in the outputs 35 10 2 Functional problems 35 10 2 1...

Page 5: ...The use of unauthorised or inappropriate components in conjunction with the emergency lighting system Incorrect installation 1 3 Parts Defective components may only be replaced by original DAISALUX pa...

Page 6: ...1 Operating instructions Always read the instructions for mounting and start up before installing the system These instructions contain important information about safety use and maintenance and prot...

Page 7: ...nalogue input 0 to 10V to regulate the brightness of one or more outputs defined as beacons Four auxiliary inputs configurable by the user Optional Ethernet or wireless connection module By LPSLan acc...

Page 8: ...4 USER MANUAL 4 1 Design and structure of the LPS centralised power unit LPS24 26 LPS24 65 1 Cable input 2 Connections 3 Control Panel 4 Converter 230 or 110VAC 24VDC 5 Battery Type of centralised pow...

Page 9: ...of discharge is estimated remaining duration less than 10 mins Stopping Occurs in any of the following situations Battery open or in bad state Incorrectly connected battery Battery voltage equal or le...

Page 10: ...150 Protection Overcurrent 4 1 A Overvoltage 34V Short circuit 12 24 A constant current up to thermal protection Self resetting detection 20s Overtemperature 80 C Protection of outputs from overtempe...

Page 11: ...that the wall where it is installed is strong enough to support the weight of the entire centralised power unit and that the mountings used are adequate to support the weight The batteries are not in...

Page 12: ...s soon as possible After assembling the centralised power unit remove the battery fuse before proceeding with the following points Then connect the battery cables and terminals supplied When connectin...

Page 13: ...exceed the system output power See 5 Technical data Check the compatibility of each luminaire connected to an output circuit configured as beacons as not all beacons allow such functionality The ELC...

Page 14: ...witching on all luminaires due to power failure in another part of the facility Switch On off Switching on on activation of the input or off on deactivating the input the circuits associated to the au...

Page 15: ...ere are four dry contacts three of them fixed according to the EN 50171 standard and the fourth configurable by the user Available options Option details Default configuration of the contacts 1 2 3 4...

Page 16: ...on test is scheduled to run on a particular date Battery charge failure Battery charge regulation fault x x Rectifier failure Failure in the rectifier x x Battery discharging Battery discharging x End...

Page 17: ...d through the display by selecting the percentage desired by circuit or by this 0 10V input which is controlled by an analogue signal from 0 to 10V or potentiometer 30K the latter is not linear Regula...

Page 18: ...fuses Activate the main power supply Before performing any operating test make sure to charge the batteries for at least 24 hours Configure the circuit according to the desired load ELC luminaires bea...

Page 19: ...circuit the battery must be disconnected from the system and the emergency lighting system will not be available therefore it must only be performed when failure of the emergency lighting system does...

Page 20: ...dules power input rectifier contactor battery and output circuits To access the system s menu press OK Overview On the different screens there are a number of symbols that can be pressed for different...

Page 21: ...e 24 3 C Charge 100 20 0Ah Status ok Gen Bat Rect Fails Vbat Battery voltage VbatInt Mid battery voltage To determine whether the two batteries are balanced Ibat Battery charge discharge current Tempe...

Page 22: ...Rect FAILURES Low security Gen Bat Rect Fails List of faults and alerts detected in the device See 8 2 7 1 faults marked with are those that can be seen on this screen 8 2 2 Test 8 2 2 1 Function tes...

Page 23: ...ast test 07 05 16 100 Automatic yes Period days 365 Test Time 23 30 Weekday Sunday Status on course Schedule test 07 12 2016 Run test Func Dur Cap Last test Indicates the date mm dd yy and result of t...

Page 24: ...tes the simulated consumption with which the capacity test is performed Cancel Launch test It enables a capacity test to be ordered or cancelled if it is running One option or another or none is displ...

Page 25: ...nge of daylight saving time European change to daylight saving time on the last Sunday of March and back to winter time on the last Sunday in October Other change to daylight saving time according to...

Page 26: ...have been configured it connects terminals 1 and 2 Configurable alerts System working Mains failure 8 2 3 3 Auxiliary inputs The LPS24 device has four auxiliary inputs Use this screen to check their s...

Page 27: ...device the above information will not appear and instead the text no gateway will be displayed Overview OK Main menu Config OK Gatew OK GATEWAY BOARD Reset web server Mode DCHP IP address 192 168 106...

Page 28: ...t some point has exceeded the alert limit for overload Check the load connected to the circuit and to correct it run a circuit test section 12 1 1 Electronic fail fault in electronic circuit component...

Page 29: ...e made at the luminaire level P lum fail only available for Non communicated type circuits Deactivate or configure a threshold in watts w to generate an alarm if consumption is above or below the thre...

Page 30: ...he luminaires will be displayed not located and 1 to 6 Serial number select with and the various luminaires on the selected circuit Status displays the status of the ELC luminaire Communication loss t...

Page 31: ...rly if it is running Battery charge 100 send a command to the device to place the battery charge estimate to 100 Uninstall lumin if there is any uninstallable luminaire to be uninstallable it must hav...

Page 32: ...e of scenario Action action to execute when the scenario runs The scenarios screen can display only the scenarios programmed on the device To generate a scenario use the WinCB software or the LPSLAN m...

Page 33: ...test Circuit test on course The device is running a circuit test Duration test required The duration test period has transpired without a test having been performed A test must be run to check the sys...

Page 34: ...inspections With the aim of maintaining equipment in optimal operating conditions annual inspection is recommended EN50171 requires at least one installation test during this period of time 9 1 2 Defi...

Page 35: ...its stipulated in this manual A circuit test can be conducted to verify that the voltage connected to said outlet is correct 10 1 2 Over consumption in the outputs If the device has signalled an outpu...

Page 36: ...device because the total power demanded exceeds the maximum admissible for the device Once the device s load is adjusted run a functional test to eliminate the overload alarm If the fault persists ca...

Page 37: ...tery duration fault When the device notifies a duration fault check the following Device s output power must be within the ranges described in this manual If the power is excessive it is outside of sp...

Page 38: ...nd an installation of devices and emergency equipment using the ON OFF button on the front panel The basic operation in the absence of POWER is OFF sends a command to the LPS24 devices to go to standb...

Page 39: ...www daisalux com 39 LPS24 USER MANUAL B SCH...

Reviews: