4
|
Components
Service manual
62
RXTM-R+RXTP-R+ARXTP-R+RXTA-B+FTXTA30B2V1B(W)
(B)+35M5V1B
R32 Optimized Heating 4 Split
ESIE21-12A – 2022.02
INFORMATION
Note the position of the Faston connectors on the compressor wire terminals to
allow correct connection during installation.
V
U
W
U
Wire terminal U
V
Wire terminal V
W
Wire terminal W
4
Set the Megger voltage to 500 V DC or 1000 V DC.
5
Measure the insulation resistance between the following terminals. The
measured insulation resistance MUST be >3 MΩ.
▪
U–ground,
▪
V–ground,
▪
W–ground.
Compressor insulation measurements
are correct?
Action
Yes
Compressor is OK. Return to
troubleshooting of the specific error
and continue with the next procedure.
No
Replace the compressor, see
4.2.2 Repair procedures
To remove the compressor insulation
Prerequisite:
Stop the unit operation via the user interface.
Prerequisite:
Turn OFF the respective circuit breaker.
Prerequisite:
Remove the required plate work, see
144].
1
Detach all the strings.
Summary of Contents for RXTA30B2V1B
Page 262: ......
Page 263: ......
Page 264: ...ESIE21 12A 2022 02 Copyright 2021 Daikin Verantwortung f r Energie und Umwelt...