background image

7

English

Outdoor Unit Installation

Flare nut tightening torque

Gas side

Liquid side

3/8 inch (9.5mm)

1/4 inch (6.4mm)

24-1/8–29-1/2lbf • ft

(32.7-39.9N • m)

10-1/2–12-3/4Ibf • ft

(14.2-17.2 N • m)

Width across flats

3/4 inch (19mm)

7/8 inch (22mm)

Valve cap tightening torque

12-5/8–15-3/8lbf • ft

(17.1-20.9N • m)

16–20-1/4lbf • ft

(21.6-27.4N • m)

Service port cap tightening torque

8–10-7/8lbf • ft (10.7-14.7N • m)

Cautions on pipe handling

•  Protect the open end of the pipe from dust and moisture.
•  All pipe bends should be as gentle as possible. Use a pipe bender for bending.

Selection of copper and heat insulation materials

When using commercial copper pipes and fittings, observe the following:

•  Insulation material: Polyethylene foam 

Heat transfer rate: 0.041 to 0.052W/mK (0.024 to 0.030Btu/fth°F (0.035 to 
0.045kcal/mh°C)) 

 

Be sure to use insulation that is designed for use with HVAC Systems.

• 

ACR Copper only.

•  Be sure to insulate both the gas and liquid piping and observe the insulation 

dimensions as below.

Be sure to 
place a cap.

Wall

Rain

If no flare cap is 

available, cover 

the flare mouth 

with tape to 
keep dirt and 
water out.

Piping size

Minimum bend radius

Piping thickness

Thermal insulation size

Thermal insulation 

thickness

Gas side

O.D. 3/8 inch

(9.5mm)

1-3/16 inch (30mm) 

or more

0.031 inch (0.8mm)

(C1220T-O)

I.D. 15/32-19/32 inch

(12-15mm)

13/32 inch

(10mm) Min.

Liquid side

O.D. 1/4 inch

(6.4mm)

1-3/16 inch (30mm) 

or more

0.031 inch (0.8mm)

(C1220T-O)

I.D. 5/16-13/32 inch

(8-10mm)

•  Use separate thermal insulation pipes for gas and liquid refrigerant pipes.
• 

Using finishing tape, bundle and wrap the indoor unit piping and drain hose 

together so that the drain hose is below the other piping.

Finishing tape

Gas pipe

Drain hose

Liquid pipe

Liquid pipe 
insulation

Gas pipe 
insulation

5. 

Pressure test and evacuating system

WARNING

• 

Make sure that air or any matter other than refrigerant (R32) does not get into the refrigeration cycle.

•  If refrigerant gas leaks should occur, ventilate the room as soon and as much as possible.
•  R32, as well as other refrigerants, should always be recovered and never be released directly into the environment.
• 

Use tools for R32 or R410A (such as the gauge manifold, charging hose, or vacuum pump adapter).

CAUTION

• 

It is highly recommended that you do not open/close the stop valves when the outdoor temperature is below −5°F (−21°C) 

as this may result in refrigerant leakage.

01_EN_3P628775-2A.indd   7

2021/02/19   13:18:24

Summary of Contents for RXM09VVJU

Page 1: ...English Fran ais Espa ol MODELS RXM09VVJU RXM12VVJU DAIKIN ROOM AIR CONDITIONER INSTALLATION MANUAL R32 Split Series Installation manual Manuel d installation Manual de instalaci n...

Page 2: ...A massive leak can lead to oxygen depletion especially in basements and an asphyxiation hazard could occur leading to serious injury or death Do not ground units to water pipes gas pipes telephone wi...

Page 3: ...re to wear proper gloves Install drain piping to ensure proper drainage Improper drain piping may result in water leakage and property damage Insulate piping to prevent condensation Be careful when tr...

Page 4: ...one containing sulfate gas corrosion may shorten the life of the air conditioner 8 Since water will flow from the drain of the outdoor unit do not place anything under the unit which must be kept away...

Page 5: ...h wire or other means How to remove the stop valve cover 1 Remove the screw on the stop valve cover 2 Slide the stop valve cover downward to remove it How to attach the stop valve cover 1 Insert the u...

Page 6: ...orientation of the outdoor unit outlet side or use the air direction adjustment grille sold separately Outdoor Unit Installation 1 Installing the outdoor unit When installing the outdoor unit refer t...

Page 7: ...the flare nut is fitted When flaring do not over tighten and crack Check Set exactly at the position shown below A Die Flare tool for R32 or R410A Conventional flare tool Clutch type Clutch type Rigid...

Page 8: ...eep dirt and water out Piping size Minimum bend radius Piping thickness Thermal insulation size Thermal insulation thickness Gas side O D 3 8 inch 9 5mm 1 3 16 inch 30mm or more 0 031 inch 0 8mm C1220...

Page 9: ...ve Lo on the gauge manifold and stop vacuum pumping Maintain this condition for a few minutes to make sure that the compound pressure gauge pointer does not swing back 1 6 Remove the valve caps from t...

Page 10: ...trip length may cause electric shock or current leakage If the stranded wires must be used make sure to use the round crimp style terminal for connection to the power supply terminal block Place the r...

Page 11: ...the unit is exposed to direct wind provide a windbreak wall Intermittent noises may be produced by the indoor unit due to the outdoor fan turning on and off when using facility settings Do not place...

Page 12: ...tion 3 After 5 to 10 minutes close the liquid stop valve with a hexagonal wrench 4 After 2 to 3 minutes close the gas stop valve and stop forced cooling operation 5 Attach the valve cap once procedure...

Page 13: ...vibration noise No refrigerant gas leaks Incomplete cooling heating function Refrigerant gas and liquid pipes and indoor drain hose extension are thermally insulated Water leakage Draining line is pro...

Page 14: ...3P628775 2A M20B074A 2102 HT The two dimensional bar code is a manufacturing code...