6
System preparation
6
Check that the following have been planned at the installation site:
A
an
electrical system
compliant with current regulations and with specifications that meet the
needs of the unit;
B
a
floor or wall drain, with siphon,
connected to the sewer system;
C
an
aeraulic system
(ducts for the air to be conveyed to the rooms.
Check that the
floor
of the place chosen for installation is:
• perfectly
flat and without any roughness
;
• vibration
resistant
;
•
able to support the weight of the equipment
considering an appropriate safety margin
(see technical data table on page 10).