20
|
Configuration
Installer and user reference guide
108
LRYELRNUN5A7Y1
CO₂ Conveni-Pack outdoor unit
4P605460-1 – 2020.08
20 Configuration
In this chapter
20.1 Overview: Configuration
This chapter describes what you have to do and know to configure the system after
it is installed.
It contains information about:
▪
Making field settings
INFORMATION
It is important that all information in this chapter is read sequentially by the installer
and that the system is configured as applicable.
DANGER: RISK OF ELECTROCUTION
20.2 Making field settings
20.2.1 About making field settings
To configure the outdoor unit and capacity up unit, you must give input to the
main PCB (A1P) of the outdoor unit and capacity up unit. This involves the
following field setting components:
▪
Push buttons to give input to the PCB
▪
A 7-segment display to read feedback from the PCB
▪
DIP switches to set the target evaporating temperature for the refrigeration side
20.2.2 To access the field setting components
You do not have to open the complete electrical component box to access the field
setting components.
1
Open the front panel (middle front panel in case of outdoor unit). See
"15.2.2 To open the outdoor unit"
58].
2
Open the inspection hole cover (left), and turn OFF the operation switch.
3
Open the inspection hole cover (right), and make the field settings.