Daikin EWLD J Series Installation, Operation And Maintenance Manual Download Page 12

D-EIMWC01008-16EU - 12/20 

       this to avoid compressor damage! 
        

3.    After completion of procedure step 2, perfo

rm an “initial   

       

start” test: 

3.1  Start the compressor and wait for the compressor to go  
       through the star/delta. 
       Carefully check during start-up. 
 

  that compressor is not producing any abnormal 

 noise or vibration; 
 

  that high pressure rises and low pressure drops  

    within 10 seconds after to evaluate if the   
    compressor is not operating in reverse due to  
    wrong wiring;  
 

  that no safeties are activated. 

 

3.2   Stop the compressor after 10 seconds. 
 

Fine-tuning of refrigerant charge while unit is in 
operation 
 

4.

     

Use the 

1/4” SAE Flare valve on the suction for fine- 

        

tuning of the refrigerant charge and make sure to  

         charge the refrigerant in its liquid state. 
 
4.1    For fine-tuning of the refrigerant charge, the compressor  
         must operate at full load (100%). 
 
4.2    Verify the superheat and subcooling: 

 

  superheat must be between 3 and 8 K 

 

  subcooling must be between 3 and 8 K 

 

4.3   Verify the oil sightglass. Level must be within the  
        sightglass. 
 
4.4   Verify the liquid line sightglass. It should be sealed  
        and not indicate moisture in the refrigerant. 
 
4.5   As long as the liquid-line sightglass is not sailed,  
        add refrigerant in steps of 1 Kg and wait until the       
        

unit runs in stable conditions. 

     Repeat the complete procedure step 4 until the liquid line 
     sightglass is sealed. 
     The unit must have the time to stabilize which means that  
     this charghing has to be done in a smooth way. 
 
5.  Note down the superheat and subcoolingfor future  
     reference. 
 
6.  Fill out the total refrigerant charge on the unit nameplate  
     and on the refrigerant charge label supplied with the  
     product. 
 

NOTE   

Take care for contamination of the remote condenser 

               In order to avoid blocking of the system. It is  
               impossible for  the manufacturer  to control the  
               contamin

ation of  the “foreign” condenser of the    

               installer. The unit has a strict contamination level. 
 

11.  PREPARING, CHECKING AND 

CONNECTING THE WATER CIRCUIT 

 

The units are equipped with a water inlet and water 
outlet for connection to a chiller water circuit. This circuit 
must be provided by a licensed technician and must 
comply with all relevant European and national 
regulations.

  

 

   

If air or dirt gets in the water circuit, problems may   

 

         occur. Therefore,  always  take  into  account  the   
          following  when connecting the water circuit:                     

1.

 

Use clean pipes only. 

2. 

Hold the pipe end downwards when removing  

       

burrs. 

3.

 

Cover the pipe end when inserting it through a 

    wall so that no dust and dirt enter.  
 

1. 

Preparing the unit for connection to the 

water circuit   

        

A  box  containing  Victaulic

®   

couplings and  a  filter  is   

          delivered with the unit. 
 
 
 
 
 
 
 
 
 

 

 

Water inlet of the evaporator 

Flowswitch 

Inlet water sensor 

Water inlet pipe containing the flowswitch and 

the water inlet temperature sensor 

Victaulic® coupling 

Counter pipe 

Field water pipe circuit 

Filter 

Filter and cup 

 
As  not  to  damage  the  parts  of  the  units  during 
transport,  the  water  inlet  pipe  with  the  flowswitch 
and  the  water  inlet  temperature  sensor  and  the 
water  outlet pipe  with  the  outlet water  temperature 
sensor, are not factory mounted. 

 

Connecting  the  water  inlet  pipe  containing 
the  flowswitch. 

         The water inlet pipe containing the  
        flowswitch.is mounted on the side of the 
          water inlet of the evaporator(s) and is pre- 
          insulated. 
         Cut  the  tie  wraps  and  fix  the  pipe  with  the   
              supplied  Victaulic

® 

couplings to the  

          evaporator inlet(s).

 

 

Connecting the water outlet pipe. 

          The water outlet pipe is mounted on the  

Summary of Contents for EWLD J Series

Page 1: ...Condenserless water cooled screw chillers EWLD110J SS EWLD265J SS EWLH 80J SS EWLH190J SS EWLS 110J SS EWLS270J SS Refrigerant R 134a R1234ze R513A English 2 Deutsch 13 Fran ais 25 Nederlands 36 Espa...

Page 2: ...to replace such personnel EWWD120J SS 280J SS EWWH090J SS 200J SS EWWS120J SS 270J SS EWLD 110J SS 265J SS EWLH 80J SS 190J SS EWLS 110J SS 270J SS Label Identification 1 Unit nameplate data 5 Manufa...

Page 3: ...1234ZE 9 8 5 ADDITIONAL GUIDELINES FOR SAFE USE OF R1234ZE E FOR EQUIPMENT LOCATED IN THE OPEN AIR 9 8 6 ADDITIONAL GUIDELINES FOR SAFE USE OF R1234ZE E FOR EQUIPMENT LOCATED IN A MACHINERY ROOM 9 9 M...

Page 4: ...PER INSTALLATION OR ATTACHEMENT OF EQUIPMENT OR ACCESSORIES COULD RESULT IN ELECTRIC SHOCK SHORT CIRCUIT LEAKS FIRE OR OTHER DAMAGE TO THE EQUIPMENT BE SURE ONLY TO USE ACCESSORIES MADE BY DAIKIN WHIC...

Page 5: ...1600 1607 Operation weight Kg 1663 1675 Connections Chilled water inlet outlet 2 inch 3 Condenser water inlet outlet 2 inch 4 2 Victaulic coupling Model EWLD J 110 130 145 165 195 Dimensions HxWxL mm...

Page 6: ...ion with Glycol Fixed minimum capacity at 100 2 Operation with Glycol below 4 C Evap LWT 3 Some units could work partialized in this area EWWH J EWLH J 1 Operation with Glycol Fixed minimum capacity a...

Page 7: ...ing in the unit to a minimum It drilling is impreventable remove the iron filling thoroughly in order to prevent surface rust 6 UNPACKING AND PLACING THE UNIT 1 Remove the wooden beams from the unit 2...

Page 8: ...1 66 19 33 10 2 01 9 4 01 29 7 27 48 12 53 67 19 78 9 2 09 10 4 15 30 7 48 49 12 85 68 20 23 8 2 17 11 4 29 31 7 70 50 13 18 69 20 69 7 2 26 12 4 43 32 7 92 51 13 51 70 21 16 6 2 34 13 4 58 33 8 15 52...

Page 9: ...ity with the directives along with the documentation Before machine installation and commissioning the people involved in this activity must have acquired the information necessary to carry out these...

Page 10: ...e done with due consideration of local airflow patterns accounting for location sources of ventilation and louvers Consideration shall also be given to the possibility of mechanical damage or contamin...

Page 11: ...technicians Before beginning any work on the system the personnel shall assure that all security precautions have been taken Always protect the operating personnel with personal protective equipment a...

Page 12: ...the product NOTE Take care for contamination of the remote condenser In order to avoid blocking of the system It is impossible for the manufacturer to control the contamination of the foreign condens...

Page 13: ...ansmitting vibration and noise 6 For units in double circuit configuration with common leaving water control ELWT be sure to foresee an insertion hole for the additional water temperature sensor Senso...

Page 14: ...relef valve on the condenser and pipe to each pressure relief valve on the evaporator Cross section and length of the discharge line must comply with local codes 15 FIELD WIRING All field wiring and...

Page 15: ...sent to specific refuse collection centres Oil must be collected and sent to specific refuse collection centres 16 BEFORE STARTING The unit should not be started not even for a very short period of ti...

Page 16: ...p VFD D L Demand Limit DI Digital Inputs DO Digital Outputs DPS Double Set Point EF Esternal Fault EFS Evaporator Flow Switch EFS 1 Evaporator Flow Switch 1 EFS 2 Evaporator Flow Switch 2 GA General A...

Page 17: ...D EIMWC01006 11EU 17 20 17 FACTORY AND FIELD CHARGED UNITS INSTRUCTIONS Errore Non si possono creare oggetti dalla modifica di codici di campo 18 FIELD CHARGED UNITS INSTRUCTIONS...

Page 18: ...rigerant charge Factory Field h Greenhouse gas emission of the total refrigerant charge expressed as tonnes of CO2 equivalent m Refrigerant type n GWP Global Warming Potential p Unit serial number 2 T...

Page 19: ...of its content and the products and services presented therein Specification are subject to change without prior notice Refer to the data communicated at the time of the order Daikin Applied Europe S...

Page 20: ...D EIMWC01006 11EU 20 20...

Reviews: