7 Commissioning
Installation manual
27
ETVH/9W(G)
Daikin Altherma 3 H HT F
4P586454-1B – 2020.01
7.2.2
To perform an air purge
Conditions:
Make sure all operation is disabled. Go to [C]:
Operation
and turn off
Room
,
Space heating/cooling
and
Tank
operation.
1
Set the user permission level to Installer. See
change the user permission level"
—
2
Go to [A.3]:
Commissioning
>
Air purge
.
3
Select
OK
to confirm.
Result:
The air purge starts. It stops automatically
when air purge cycle is finished.
To stop the air purge manually:
—
1
Go to
Stop air purge
.
2
Select
OK
to confirm.
7.2.3
To perform an operation test run
Conditions:
Make sure all operation is disabled. Go to [C]:
Operation
and turn off
Room
,
Space heating/cooling
and
Tank
operation.
1
Set the user permission level to
Installer
change the user permission level"
—
2
Go to [A.1]:
Commissioning
>
Operation test
run
.
3
Select a test from the list.
Example:
Heating
.
4
Select
OK
to confirm.
Result:
The test run starts. It stops automatically
when ready (±30 min).
To stop the test run manually:
—
1
In the menu, go to
Stop test run
.
2
Select
OK
to confirm.
INFORMATION
If the outdoor temperature is outside the range of
operation, the unit may NOT operate or may NOT deliver
the required capacity.
To monitor leaving water and tank temperatures
During test run, the correct operation of the unit can be checked by
monitoring its leaving water temperature (heating/cooling mode) and
tank temperature (domestic hot water mode).
To monitor the temperatures:
1
In the menu, go to
Sensors
.
2
Select the temperature information.
7.2.4
To perform an actuator test run
Conditions:
Make sure all operation is disabled. Go to [C]:
Operation
and turn off
Room
,
Space heating/cooling
and
Tank
operation.
Purpose
Perform an actuator test run to confirm the operation of the different
actuators. For example, when you select
Pump
, a test run of the
pump will start.
1
Set the user permission level to Installer. See
change the user permission level"
—
2
Go to [A.2]:
Commissioning
>
Actuator test run
.
3
Select a test from the list.
Example:
Pump
.
4
Select
OK
to confirm.
Result:
The actuator test run starts. It stops
automatically when ready (±30 min).
To stop the test run manually:
—
1
In the menu, go to
Stop test run
.
2
Select
OK
to confirm.
Possible actuator test runs
▪
Backup heater 1
test
▪
Backup heater 2
test
▪
Pump
test
INFORMATION
Make sure that all air is purged before executing the test
run. Also avoid disturbances in the water circuit during the
test run.
▪
Shut off valve
test
▪
Diverter valve
test (3-way valve for switching between space
heating and tank heating)
▪
Bivalent signal
test
▪
Alarm output
test
▪
C/H signal
test
▪
DHW pump
test
7.2.5
To perform an underfloor heating screed
dryout
Conditions:
Make sure all operation is disabled. Go to [C]:
Operation
and turn off
Room
,
Space heating/cooling
and
Tank
operation.
1
Set the user permission level to Installer. See
change the user permission level"
18].
—
2
Go to [A.4]:
Commissioning
>
UFH screed dryout
.
3
Set a dryout program: go to
Program
and use the
UFH screed dryout programming screen.
4 Select
OK
to confirm.
Result:
The underfloor heating screed dryout starts.
It stops automatically when done.
To stop the test run manually:
—
1
Go to
Stop UFH screed dryout
.
2
Select
OK
to confirm.
NOTICE
To perform an underfloor heating screed dryout, room frost
protection needs to be disabled ([2‑06]=0). By default, it is
enabled ([2‑06]=1). However, due to the "installer-on-site"
mode (see "Commissioning"), room frost protection will be
automatically disabled for 12 hours after the first power-on.
If the screed dryout still needs to be performed after the
first 12 hours of power-on, manually disable room frost
protection by setting [2‑06] to "0", and KEEP it disabled
until the screed dryout has finished. Ignoring this notice will
result in cracking of the screed.