background image

8 Commissioning

Installation manual

38

ETSH/X(B)16P30+50EF

Daikin Altherma 3 H HT ECH

O

4P679468-1A – 2022.07

4

Read out the flow rate

(a)

. If the flow rate is too low:

▪ Do air purge.

▪ Check the function of the valve motor of M1S and

M2S. Replace the valve motor if necessary.

(a)

During pump test run, the unit can operate below the minimum
required flow rate.

Minimum required flow rate

12 l/min

8.2.2

To perform an air purge

Conditions: 

Make  sure  all  operation  is  disabled.  Go  to  [C]:

Operation

  and  turn  off 

Space  heating/cooling

  and 

Tank

operation.

1

Set the user permission level to Installer. See 

"To

change the user permission level"

 [

4

 28].

2

Go to [A.3]: 

Commissioning

 > 

Air purge

.

3

Select 

OK

 to confirm.

Result: 

The air purge starts. It stops automatically

when air purge cycle is finished.

To stop the air purge manually:

1

Go to 

Stop air purge

.

2

Select 

OK

 to confirm.

8.2.3

To perform an operation test run

Conditions: 

Make  sure  all  operation  is  disabled.  Go  to  [C]:

Operation

  and  turn  off 

Space  heating/cooling

  and 

Tank

operation.

1

Set the user permission level to 

Installer

. See 

"To

change the user permission level"

 [

4

 28].

2

Go to [A.1]: 

Commissioning

 > 

Operation test

run

.

3

Select a test from the list. 

Example: 

Heating

.

4

Select 

OK

 to confirm.

Result: 

The test run starts. It stops automatically

when ready (±30 min).

To stop the test run manually:

1

In the menu, go to 

Stop test run

.

2

Select 

OK

 to confirm.

INFORMATION

If  the  outdoor  temperature  is  outside  the  range  of
operation,  the  unit  may  NOT  operate  or  may  NOT  deliver
the required capacity.

To monitor leaving water and tank temperatures

During test run, the correct operation of the unit can be checked by
monitoring its leaving water temperature (heating/cooling mode) and
tank temperature (domestic hot water mode).

To monitor the temperatures:

1

In the menu, go to 

Sensors

.

2

Select the temperature information.

8.2.4

To perform an actuator test run

Purpose

Perform an actuator test run to confirm the operation of the different
actuators.  For  example,  when  you  select 

Pump

,  a  test  run  of  the

pump will start.

Conditions: 

Make  sure  all  operation  is  disabled.  Go  to  [C]:

Operation

  and  turn  off 

Space  heating/cooling

  and 

Tank

operation.

1

Set the user permission level to Installer. See 

"To

change the user permission level"

 [

4

 28].

2

Go to [A.2]: 

Commissioning

 > 

Actuator test run

.

3

Select a test from the list. 

Example: 

Pump

.

4

Select 

OK

 to confirm.

Result: 

The actuator test run starts. It stops

automatically when ready (±30 min).

To stop the test run manually:

1

In the menu, go to 

Stop test run

.

2

Select 

OK

 to confirm.

Possible actuator test runs

NOTICE

For the backup heater test run, make sure that at least one
of the two mixing valves of the unit is open during the test.
Otherwise the thermal cut-out of the backup heater may be
triggered.

Backup heater 1

 test

Backup heater 2

 test

Pump

 test

INFORMATION

Make  sure  that  all  air  is  purged  before  executing  the  test
run. Also avoid disturbances in the water circuit during the
test run.

Shut off valve

 test

DHW signal

 

test

Bivalent signal

 test

Alarm output

 test

C/H signal

 test

DHW pump

 test

Tank valve

 test

Bypass valve

 test

Bizone  kit  direct  pump

  test  (bizone  kit  EKMIKPOA  or

EKMIKPHA)

Bizone  kit  mixed  pump

  test  (bizone  kit  EKMIKPOA  or

EKMIKPHA)

Bizone  kit  mixing  valve

  test  (bizone  kit  EKMIKPOA  or

EKMIKPHA)

8.2.5

To perform an underfloor heating screed
dryout

Conditions: 

Make  sure  all  operation  is  disabled.  Go  to  [C]:

Operation

  and  turn  off 

Space  heating/cooling

  and 

Tank

operation.

1

Set the user permission level to Installer. See 

"To

change the user permission level"

 [

4

 28].

2

Go to [A.4]: 

Commissioning

 > 

UFH screed dryout

.

3

Set a dryout program: go to 

Program

 and use the

UFH screed dryout programming screen.

Summary of Contents for ETSHB16P50EF

Page 1: ...l Daikin Altherma 3 H HT ECH O English Installation manual Daikin Altherma 3 H HT ECH O ETSH16P30EF ETSH16P50EF ETSHB16P30EF ETSHB16P50EF ETSX16P30EF ETSX16P50EF ETSXB16P30EF ETSXB16P50EF https daikintechnicaldatahub eu ...

Page 2: ...r ovat seuraavien direktiivien tai asetusten mukaisia edellyttäen että tuotteita käytetään ohjeidemme mukaisesti jsou ve shodě s následujícími směrnicemi nebo předpisy za předpokladu že tyto výrobky jsou používány v souladu s našimi pokyny u skladu sa sljedećom direktivom ma ili odredbom a uz uvjet da se proizvodi koriste sukladno našim uputama megfelelnek az alábbi irányelv ek nek vagy egyéb szab...

Page 3: ...ivered as accessory 26 6 3 15 To connect the solar input 26 6 3 16 To connect the DHW output 27 7 Configuration 27 7 1 Overview Configuration 27 7 1 1 To access the most used commands 28 7 2 Configuration wizard 29 7 2 1 Configuration wizard Language 29 7 2 2 Configuration wizard Time and date 29 7 2 3 Configuration wizard System 29 7 2 4 Configuration wizard Backup heater 30 7 2 5 Configuration w...

Page 4: ...and regulations Installation site see 4 1 Preparing the installation site 46 WARNING Follow the service space dimensions in this manual for correct installation of the unit See 4 1 1 Installation site requirements of the indoor unit 46 CAUTION Install the indoor unit at a minimum distance of 1 m from other heat sources 80 C e g electrical heater oil heater chimney and combustible materials Otherwi...

Page 5: ...heating electrical shock or fire Do NOT install a phase advancing capacitor because this unit is equipped with an inverter A phase advancing capacitor will reduce performance and may cause accidents WARNING The backup heater MUST have a dedicated power supply and MUST be protected by the safety devices required by the applicable legislation WARNING If the supply cord is damaged it MUST be replaced...

Page 6: ... on the plugs 4 Unit installation 4 1 Preparing the installation site 4 1 1 Installation site requirements of the indoor unit The indoor unit is designed for indoor installation only and for the following ambient temperatures Space heating operation 5 30 C Space cooling operation 5 35 C Domestic hot water production 5 35 C If EKECBUAF6V is installed ambient temperature is limited to 5 32 C INFORMA...

Page 7: ...and slide the interface panel downwards 1 2 2 Remove the switch box cover NOTICE Do NOT damage or remove the foam sealing of the switch box 3 Disconnect the ground connection from the top cover of the switch box 1 4 2 2 To lower the switch box of the indoor unit and remove the top cover During the installation you will need access to the inside of the indoor unit To have easier front access lower ...

Page 8: ...install the indoor unit 1 Lift the indoor unit from the pallet and place it on the floor Also see 3 1 2 To handle the indoor unit 46 2 Connect the drain hose to the drain See 4 3 2 To connect the drain hose to the drain 48 3 Slide the indoor unit into position NOTICE Level Make sure the unit is level 4 3 2 To connect the drain hose to the drain Spillover water from the water storage tank as well a...

Page 9: ... 1 bar Water pressure Storage tank The water inside the storage tank is not pressurized Therefore a visual check of the water level in the storage tank has to be carried out annually Water temperature All installed piping and piping accessories valve connections MUST withstand the following temperatures INFORMATION The following figure is an example and may NOT completely match your system layout ...

Page 10: ...cause malfunctioning of the unit 1 Connect the outdoor unit field piping to the water connection pipes of the indoor unit Do NOT exceed the maximum tightening torque Thread size 1 25 30 N m To avoid damage apply the necessary countertorque with a suitable tool Ø7 mm 1 2 3 2 Remove the thermal insulation of the hydraulic block Open the vent valve on the pump by one turn Afterwards put the thermal i...

Page 11: ...ooling water OUT screw connection 1 b Space heating cooling water IN screw connection 1 c Domestic hot water OUT screw connection 1 d Domestic cold water IN cold water supply screw connection 1 NOTICE It is recommended to install shut off valves on the space heating cooling water in and out connections as well as on the domestic cold water in and domestic hot water out connections These shut off v...

Page 12: ...lace maintenance parts replacement 5 2 3 To fill the heating system DANGER RISK OF ELECTROCUTION During the filling process water can escape from any leaking point and can cause an electrical shock if it comes into contact with live parts Before the filling process de energise the unit After the first filling and before switching on the unit with the mains switch check whether all electric parts a...

Page 13: ...eeze up after all Take preventive actions to ensure a minimal exposure of the glycol to air NOTICE Use ONLY propylene glycol including the required inhibitors classified as category III as per EN1717 Required concentration of glycol The required concentration of glycol depends on the lowest expected outdoor temperature and on whether you want to protect the system from bursting or from freezing To...

Page 14: ...leaks 5 2 6 To fill the storage tank NOTICE Before the storage tank can be filled the heat exchangers inside the storage tank have to be filled see previous chapters Fill the storage tank with a water pressure 6 bar and a flow speed 15 l min Without installed drainback solar kit option 1 Connect a hose with non return valve 1 2 to the drainback connection 2 Fill the storage tank until water spills...

Page 15: ...t source control See 6 3 10 To connect the changeover to external heat source 422 Power consumption digital inputs See 6 3 11 To connect the power consumption digital inputs 423 Safety thermostat See 6 3 12 To connect the safety thermostat normally closed contact 423 Smart Grid See 6 3 13 To connect a Smart Grid 424 Item Description WLAN cartridge See 6 3 14 To connect the WLAN cartridge delivered...

Page 16: ...it Installation manual of the wired room thermostat digital or analogue multi zoning base unit Addendum book for optional equipment In this case You need to connect the wired room thermostat digital or analogue to the multi zoning base unit You need to connect the multi zoning base unit to the outdoor unit For cooling heating operation you also need to implement a relay field supply see addendum b...

Page 17: ... of normal kWh rate power supply Interconnection cable Wires 3 GND 1 5 mm Power supply indoor unit Wires 1N GND Maximum running current 6 3 A A 2x B X1M 1 2 3 4 5 6 A B 2x b a a 1 2 3 b L N F2B 1 3 2 4 I I Q DI 2 6 5 230 6 3 A V AC 1N 50 Hz a Interconnection cable b Power supply indoor unit In case of preferential kWh rate power supply Interconnection cable Wires 3 GND 1 5 mm Power supply indoor u...

Page 18: ...ccordance with the backup heater capacity as listed in the table below Backup heater type Backup heater capacity Power supply Maximum running current Zmax 3V 1 kW 1N 230 V 4 4 A 2 kW 1N 230 V 8 7 A 3 kW 1N 230 V 13 1 A 6V 2 kW 1N 230 V 8 7 A 4 kW 1N 230 V 17 4 A a b 0 22 Ω 6 kW 1N 230 V 26 1 A a b 0 22 Ω 9W 3 kW 3N 400 V 4 A 6 kW 3N 400 V 9 A 9 kW 3N 400 V 13 A a Electrical equipment complying wit...

Page 19: ... 2 3 4 F1B 32A I I 9W 3N 400 V 3N 50 Hz 400 V AC SWB2 Q1DI L1 L2 L3 N X6M 1 2 3 4 5 6 F1B 20A I I I F1B Overcurrent fuse field supply Recommended fuse tripping class C Q1DI Earth leakage circuit breaker field supply SWB Switch box X6M Terminal field supply 6 3 4 To connect the backup heater to the main unit Wires The connection cables are already connected to the option backup heater EKECBU 9 3 Ba...

Page 20: ...Top cover 2 Connect the valve control cable to the appropriate terminals as shown in the illustration below NOTICE Wiring is different for a NC normally closed valve and a NO normally open valve A B M2S B 14 18 X 2M 1 NO B 13 18 X 2M 1 NC A 3 Fix the cable with cable ties to the cable tie mountings General information see 6 3 1 To connect the electrical wiring to the indoor unit 416 6 3 6 To conne...

Page 21: ...ndoor unit 47 1 User interface panel 1 3 4 2 2 Switch box 3 Switch box cover 4 Top cover 2 Connect the domestic hot water pump cable to the appropriate terminals as shown in the illustration below B A B 1 M M2P X 2M 1 7 8 A 3 Fix the cable with cable ties to the cable tie mountings General information see 6 3 1 To connect the electrical wiring to the indoor unit 416 6 3 8 To connect the alarm outp...

Page 22: ...he space cooling heating ON OFF output cable to the appropriate terminals as shown in the illustration below A B B 5 6 X 2M 1 N L Space C H On OFF output Max load 0 3 A 230 V AC 1 A 5 V DC 5 6 A 3 Fix the cable with cable ties to the cable tie mountings General information see 6 3 1 To connect the electrical wiring to the indoor unit 416 6 3 10 To connect the changeover to external heat source INF...

Page 23: ...he following see 4 2 1 To open the indoor unit 47 1 User interface panel 1 3 4 2 2 Switch box 3 Switch box cover 4 Top cover 2 Install the switch box metal insert 1 2 3 3 Connect the power consumption digital inputs cable to the appropriate terminals as shown in the illustration below A B B A A8P M 1 0 8 X 1 2 3 4 5 1 2 4 5 S 6 S S 7 S S 8 S S 9 S 3 a 4 Fix the cable with cable ties to the cable t...

Page 24: ...thermostat after it is installed Without configuration the unit will ignore the safety thermostat contact 6 3 13 To connect a Smart Grid This topic describes 2 possible ways to connect the indoor unit to a Smart Grid In case of low voltage Smart Grid contacts In case of high voltage Smart Grid contacts This requires the installation of the Smart Grid relay kit EKRELSG The 2 incoming Smart Grid con...

Page 25: ...Grid in case of high voltage contacts is as follows S4S 9 10 X 5M 1 X 5M 1 7 8 K2A K1A 5 6 3 4 K1A L N L N STEP 3 a b c d e f STEP 1 STEP 2 A1 A2 25 24 25 23 X1 M 2 K2A A1 A2 2 1 STEP 1 Smart Grid relay kit installation STEP 2 Low voltage connections STEP 3 High voltage connections 1 High voltage Smart Grid contact 1 2 High voltage Smart Grid contact 2 a b Coil sides of relays c d Contact sides of...

Page 26: ...the high voltage wiring as follows A B A B X 2M 1 24 25 X M 12 25 X M 12 24 X M 12 25 X M 12 23 1 2 23 L2 L1 N N 6 Fix the cable with cable ties to the cable tie mountings General information see 6 3 1 To connect the electrical wiring to the indoor unit 416 6 3 14 To connect the WLAN cartridge delivered as accessory D Wireless gateway 1 Insert the WLAN cartridge into the cartridge slot on the user...

Page 27: ... 2M 1 11 12 A B DHW output Max load 0 3 A 230 V AC 12 11 3 Fix the cable with cable ties to the cable tie mountings General information see 6 3 1 To connect the electrical wiring to the indoor unit 416 7 Configuration INFORMATION Cooling is only applicable in case of reversible models 7 1 Overview Configuration This chapter describes what you have to do and know to configure the system after it is...

Page 28: ...pin code for the user permission level Browse through the list of digits and change the selected digit Move the cursor from left to right Confirm the pin code and proceed Installer pin code The Installer pin code is 5678 Additional menu items and installer settings are now available 5678 Installer Advanced user pin code The Advanced user pin code is 1234 Additional menu items for the user are now ...

Page 29: ...nu screen and confirm whether the backup heater can take over the heat load or not Alternatively when Emergency is set to auto SH reduced DHW on space heating is reduced but domestic hot water is still available auto SH reduced DHW off space heating is reduced and domestic hot water is NOT available auto SH normal DHW off space heating operates as normally but domestic hot water is NOT available S...

Page 30: ...kup heater The capacities for the different steps of the backup heater must be set for the energy metering and or power consumption control feature to work properly When measuring the resistance value of each heater you can set the exact heater capacity and this will lead to more accurate energy data Backup heater type Code Description 9 3 1 E 03 0 None 2 3V 3 6V 4 9W Voltage For a 3V and 6V model...

Page 31: ...ximum 55 C Variable 2 Radiator Maximum 70 C Fixed 10 C NOTICE Average emitter temperature Leaving water temperature Delta T 2 This means that for a same leaving water temperature setpoint the average emitter temperature of radiators is lower than that of underfloor heating because of a bigger delta T Example radiators 40 10 2 35 C Example underfloor heating 40 5 2 37 5 C To compensate you can Incr...

Page 32: ...ature varies according to the tank temperature schedule See the operation manual for more details Settings for Reheat only mode During Reheat only mode the tank setpoint can be set on the user interface The maximum allowed temperature is determined by the following setting Code Description 5 8 6 0E Maximum The maximum temperature that users can select for the domestic hot water You can use this se...

Page 33: ...erature of the leaving water for different ambient temperatures For example if leaving water temperature is in general fine but at low ambient temperatures too cold raise the slope so that leaving water temperature is heated increasingly more at decreasingly lower ambient temperatures Change the offset to equally increase or decrease the temperature of the leaving water for different ambient tempe...

Page 34: ...estriction Only available to installers 5 C Tank WD curve INFORMATION Maximum and minimum setpoints You cannot configure the curve with temperatures that are higher or lower than the set maximum and minimum setpoints for that zone or for the tank When the maximum or minimum setpoint is reached the curve flattens out To fine tune the weather dependent curve slope offset curve The following table de...

Page 35: ...le in external room thermostat control For more info about the functionality see 7 4 1 Main zone 434 Code Description 3 A C 06 External room thermostat type for the additional zone 1 1 contact 2 2 contacts 7 4 3 Information Dealer information The installer can fill in his contact number here Code Description 8 3 N A Number that users can call in case of problems ...

Page 36: ...operation mode Allow electrical heaters Limit setting kW Enable room buffering Allow heater Allow pump 9 9 Power consumption control Power consumption control Type Limit Limit 1 Limit 2 Limit 3 Limit 4 Priority heater BBR16 activation BBR16 power limit 9 Installer settings Configuration wizard Domestic hot water Backup heater Emergency Balancing Water pipe freeze prevention Benefit kWh power suppl...

Page 37: ...ring has been carried out according to this document and the applicable legislation Between the local supply panel and the outdoor unit Between indoor unit and outdoor unit Between the local supply panel and the indoor unit Between the indoor unit and the valves if applicable Between the indoor unit and the room thermostat if applicable The system is properly earthed and the earth terminals are ti...

Page 38: ...t water mode To monitor the temperatures 1 In the menu go to Sensors 2 Select the temperature information 8 2 4 To perform an actuator test run Purpose Perform an actuator test run to confirm the operation of the different actuators For example when you select Pump a test run of the pump will start Conditions Make sure all operation is disabled Go to C Operation and turn off Space heating cooling ...

Page 39: ...tall an electric backup heater to ensure safe operation for all conditions Drain back models For drain back models a backup heater EKECBUA must always be installed For drain back models the factory setting of field code C 02 is set to 0 Bivalent models For bivalent models the factory setting of the field code C 02 is set to 2 It is assumed that a controllable bivalent external heat source is conne...

Page 40: ...connection 1 a2 Space heating cooling Water OUT screw connection 1 b1 DHW Cold water IN screw connection 1 b2 DHW Hot water OUT screw connection 1 c1 Water IN from outdoor unit screw connection 1 c2 Water OUT to outdoor unit screw connection 1 d1 Water IN from bivalent heat source screw connection 1 d2 Water OUT to bivalent heat source screw connection 1 e Pump f Backup heater g Shut off valve fem...

Page 41: ... OFF thermostat wired On OFF thermostat wired On OFF thermostat wireless On OFF thermostat wireless Ext thermistor External thermistor Heat pump convector Heat pump convector Position in switch box English Translation Position in switch box Position in switch box SWB1 Main switch box SWB2 Backup heater switch box Legend A1P Main PCB A2P On OFF thermostat PC power circuit A3P Heat pump convector A8...

Page 42: ... Normally closed Normally open Normally open Note outputs can be taken from terminal positions X12M 17 L 18 N and X12M 17 L 11 N Max 2 outputs at once are possible this way Note outputs can be taken from terminal positions X12M 17 L 18 N and X12M 17 L 11 N Max 2 outputs at once are possible this way Preferential kWh rate power supply contact 16 V DC detection voltage supplied by PCB Preferential k...

Page 43: ...5M 3 4 2 core 2x0 75 2 core 2x0 75 X15M 7 8 X15M 8 X15M 7 2 Safety thermostat Q4L 2 1 Smartgrid contact K1A Smartgrid relais K1A Smartgrid relais K2A X12M 23 25 2 core 2x0 75 X12M 24 25 2 core 2x0 75 Optional part Only for HV smartgrid signal Only for LV smartgrid 1 Smartgrid contact S10S FIELD SUPPLY X15M 5 6 signal Electricity meter pulse input 1 2 core X15M 9 10 Electricity meter pulse input 2 ...

Page 44: ...4P679468 1A 2022 07 Copyright 2022 Daikin 4P679468 1 A 0000000A Verantwortung für Energie und Umwelt ...

Reviews: