3 About the box
Installation manual
4
ELSH/X(B)12P30+50E
Daikin Altherma 3 R MT ECH
₂
O
4P708484-1 – 2023.03
15])
DANGER: RISK OF ELECTROCUTION
During the filling process, water can escape from any
leaking point and can cause an electrical shock if it comes
into contact with live parts.
▪ Before the filling process, de-energise the unit.
▪ After the first filling and before switching on the unit
with the mains switch, check whether all electric parts
and connection points are dry.
WARNING
The field piping method MUST be in accordance with the
instructions
from
this
manual.
See
WARNING
Install the tundish away from any electrical device.
Possible consequence:
Electrical shock or fire.
Electrical installation (see
DANGER: RISK OF ELECTROCUTION
DANGER: RISK OF ELECTROCUTION
During the filling process, water can escape from any
leaking point and can cause an electrical shock if it comes
into contact with live parts.
▪ Before the filling process, de-energise the unit.
▪ After the first filling and before switching on the unit
with the mains switch, check whether all electric parts
and connection points are dry.
WARNING
Electrical wiring connection method MUST be in
accordance with the instructions from:
▪ This manual. See
▪ The wiring diagram, which is delivered with the unit,
located on the inside of the indoor unit switch box
cover. For a translation of its legend, see
WARNING
▪ All wiring MUST be performed by an authorised
electrician and MUST comply with the applicable
national wiring regulation.
▪ Make electrical connections to the fixed wiring.
▪ All components procured on-site and all electrical
construction MUST comply with the applicable
legislation.
WARNING
If the supply cord is damaged, it MUST be replaced by the
manufacturer, its service agent or similarly qualified
persons in order to avoid a hazard.
WARNING
ALWAYS use multicore cable for power supply cables.
CAUTION
Do NOT push or place redundant cable length into the unit.
WARNING
The backup heater MUST have a dedicated power supply
and MUST be protected by the safety devices required by
the applicable legislation.
CAUTION
To guarantee the unit is completely earthed, ALWAYS
connect the backup heater power supply and the earth
cable.
INFORMATION
Details of type and rating of fuses, or rating of circuit
breakers are described in
WARNING
Be aware that the domestic hot water temperature at the
hot water tap will be equal to the value selected in field
setting [2-03] after a disinfection operation.
When the high domestic hot water temperature can be a
potential risk for human injuries, a mixing valve (field
supply) shall be installed at the domestic hot water out
connection of the storage tank. This mixing valve shall
secure that the hot water temperature at the hot water tap
never rise above a set maximum value. This maximum
allowable hot water temperature shall be selected
according to the applicable legislation.
CAUTION
The disinfection function settings MUST be configured by
the installer according to the applicable legislation.
CAUTION
Make sure that the disinfection function start time [5.7.3]
with defined duration [5.7.5] is NOT interrupted by possible
domestic hot water demand.
43])
WARNING
Commissioning method MUST be in accordance with the
instructions
from
this
manual.
See
43].
WARNING
Air purging heat emitters or collectors.
Before you
purge air from heat emitters or collectors, check if
or
is displayed on the home screen of the user interface.
▪ If not, you can purge air immediately.
▪ If yes, make sure that the room where you want to
purge air is sufficiently ventilated.
Reason:
Refrigerant
might leak into the water circuit, and subsequently into
the room when you purge air from the heat emitters or
collectors.
3
About the box
Keep the following in mind:
▪ At delivery, the unit MUST be checked for damage and
completeness. Any damage or missing parts MUST be reported
immediately to the claims agent of the carrier.
▪ Bring the packed unit as close as possible to its final installation
position to prevent damage during transport.
▪ Prepare in advance the path along which you want to bring the