Commissioning
WARNING!
Make sure that the equipment is connected to the
earth cable.
WARNING!
Make sure that the line voltage corresponds to
the voltage indicated on the equipment
identification plate.
The commissioning procedure should be completed by
following these steps:
Fill the boiler by connecting the water inlet tap and
check for any leaks from gaskets and connections.
Tighten the bolts or connections if necessary;
Do not exceed the maximum permitted pressure,
indicated in the
“general technical data” section;
Check whether the water circuit safety equipment
is working;
Connect the plug to the power socket;
When the plug is inserted, the boiler is in stand-by,
the display remains switched off, the power key is
illuminated;
Press the power key (see paragraph 8.1.3), the
equipment will start in
“ECO” mode (default
setting) 5 minutes after pressing the key.