*In situations that have multiple units, a 48” minimum clearance is
required between the condenser coils.
Adequate clearance around the unit should be kept for safety, ser-
vice, maintenance, and proper unit operation. A total clearance
of 75” on the main control panel side of the unit is recommended
to facilitate possible fan shaft, coil, and electric heat. A clearance
of 48” is recommended on all other sides of the unit to facilitate
possible compressor removal, to allow service access and to in-
sure proper ventilation and condenser airflow. The unit must not
be installed beneath any obstruction. The unit should be installed
remote from all building exhausts to inhibit ingestion of exhaust
air into the unit fresh air intake.
INSULATED
PANELS
ROOF CURB INSTALLATION
ROOF CURB POST-INSTALLATION CHECKS
After installation, check the top of the curb, duct connection frame
and duct flanges to make sure gasket has been applied properly.
Gasket should be firmly applied to the top of the curb perimeter,
duct flanges and any exposed duct connection frame. If gasket is
loose, re-apply using strong weather resistant adhesive.
P
ROTRUSION
Inspect curb to ensure that none of the utility services (electric)
routed through the curb protrude above the curb.
I
F
PROTRUSIONS
EXIST
,
DO
NO
ATTEMPT
TO
SET
UNIT
ON
CURB
.
CAUTION
ROOF TOP DUCT CONNECTIONS
Install all duct connections on the unit before placing the unit on
rooftop.
H
ORIZONTAL
D
ISCHARGE
Refer to IOD-7006 included in the literature pack for installing hori-
zontal duct covers.
Flexible duct connectors between the unit and ducts are recom-
mended. Insulate and weatherproof all external ductwork and
joints as required and in accordance with local codes.
RETURN
SUPPLY
12”
17”
7 3/8”
11”
4 7/8””
25”
6 3/16”
REMOVE
COVERS
HORIZONTAL DISCHARGE DUCT CONNECTIONS
RIGGING DETAILS
WARNING
T
O PREVENT PROPERTY DAMAGE, THE UNIT SHOULD REMAIN IN AN UPRIGHT
POSITION DURING ALL RIGGING AND MOVING OPERATIONS.
T
O FACILITATE
LIFTING AND MOVING WHEN A CRANE IS USED, PLACE THE UNIT IN AN
ADEQUATE CABLE SLING.
I
F
UNITS
ARE
LIFTED
TWO
AT
A
TIME
,
THE
FORK
HOLES
ON
THE
CONDENSER
END
OF
THE
UNIT
MUST
NOT
BE
USED
. M
INIMUM
FORK
LENGTH
IS
42”
TO
PREVENT
DAMAGE
TO
THE
UNIT
;
HOWEVER
, 48”
IS
RECOMMENDED
.
CAUTION
Provisions for forks have been included in the unit base frame. No
other fork locations are approved.
WARNING
T
O PREVENT POSSIBLE EQUIPMENT DAMAGE, PROPERTY DAMAGE, PERSONAL
INJURY OR DEATH, THE FOLLOWING BULLET POINTS MUST BE OBSERVED
WHEN INSTALLING THE UNIT.
• Unit must be lifted by the four lifting holes located at the
base frame corners.
• Lifting cables should be attached to the unit with shackles.