Test run should be performed in accordance with the

operation  manual  of  the  indoor  unit  to  make  sure  that  all  functions
and parts are working properly.

1

In  cooling  mode,  select  the  lowest  programmable  temperature.
In heating mode, select the highest programmable temperature.
Test run can be disabled if necessary.

2

When  the  test  run  is  finished,  set  the  temperature  to  a  normal
level. In cooling mode: 26~28°C, in heating mode: 20~24°C.

3

The  system  stops  operating  3  minutes  after  the  unit  is  turned
OFF.

7.2.1

To perform a test run in winter season

When operating the air conditioner in 

Cooling

 mode in winter, set it

to test run operation using the following method.

For FTXP and ATXP units

1

Press 

, and 

 simultaneously.

2

Press 

.

3

Select 

.

4

Press 

.

5

Press 

 to switch the system on.

Result: 

Test  run  operation  will  stop  automatically  after  about

30 minutes.

6

To stop operation, press 

.

For FTXF units

7

Press  to switch the system on.

8

Press the centre of 

, and 

 simultaneously.

9

Press 

 twice.

Result: 

  will  appear  on  the  display.  Test  run  operation  is

selected.  Test  run  operation  will  stop  automatically  after  about
30 minutes.

10

To stop operation, press .

INFORMATION

Some  of  the  functions  CANNOT  be  used  in  the  test  run
operation mode.

If  a  power  failure  occurs  during  operation,  the  system  automatically
restarts immediately after power is restored.

8

Disposal

Dismantling of the unit and treatment of the refrigerant, oil and other
parts MUST comply with the applicable legislation.

Summary of Contents for ATXP20L5V1B

Page 1: ...al Daikin room air conditioner English Installation manual Daikin room air conditioner FTXP20L5V1B FTXP25L5V1B FTXP35L5V1B ATXP20L5V1B ATXP25L5V1B ATXP35L5V1B FTXF20A5V1B FTXF25A5V1B FTXF35A5V1B FTXF20B5V1B FTXF25B5V1B ...

Page 2: ...нти при условие че се използват съгласно нашите инструкции atitinka žemiau nurodytus standartus ir arba kitus norminius dokumentus su sąlyga kad yra naudojami pagal mūsų nurodymus tad ja lietoti atbilstoši ražotāja norādījumiem atbilst sekojošiem standartiem un citiem normatīviem dokumentiem sú v zhode s nasledovnou ými normou ami alebo iným i normatívnym i dokumentom ami za predpokladu že sa použ...

Page 3: ... се използват съгласно нашите инструкции atitinka žemiau nurodytus standartus ir arba kitus norminius dokumentus su sąlyga kad yra naudojami pagal mūsų nurodymus tad ja lietoti atbilstoši ražotāja norādījumiem atbilst sekojošiem standartiem un citiem normatīviem dokumentiem sú v zhode s nasledovnou ými normou ami alebo iným i normatívnym i dokumentom ami za predpokladu že sa používajú v súlade s n...

Page 4: ...gmis t e standardi te ga või teiste normatiivsete dokumentidega kui neid kasutatakse vastavalt meie juhenditele съответстват на следните стандарти или други нормативни документи при условие че се използват съгласно нашите инструкции atitinka žemiau nurodytus standartus ir arba kitus norminius dokumentus su sąlyga kad yra naudojami pagal mūsų nurodymus tad ja lietoti atbilstoši ražotāja norādījumie...

Page 5: ...eep it for future reference Target audience Authorised installers INFORMATION This appliance is intended to be used by expert or trained users in shops in light industry and on farms or for commercial and household use by lay persons Documentation set This document is part of a documentation set The complete set consists of General safety precautions Safety instructions that you MUST read before i...

Page 6: ... acid deoxidised seamless copper for refrigerant Foreign materials inside pipes including oils for fabrication must be 30 mg 10 m Refrigerant piping diameter Use the same diameters as the connections on the outdoor units Class L1 liquid piping L1 gas piping 20 35 Ø6 4 Ø9 5 Refrigerant piping material Piping material Phosphoric acid deoxidised seamless copper Flare connections Only use annealed mat...

Page 7: ...ss 20 35 back on the front grille 3 Install the air filter and then mount the front panel To remove the electrical wiring box cover 1 Remove the front grille 2 Remove 1 screw from the electrical wiring box 3 Open the electrical wiring box cover by pulling the protruding part on the top of the cover 4 Unhook the tab on the bottom and remove the electrical wiring box cover a a c b a 1 3 2 a Tab b Pr...

Page 8: ...1 Bore a 65 mm large feed through hole in the wall with a downward slope towards the outside 2 Insert a wall embedded pipe into the hole 3 Insert a wall cover into the wall pipe Ø65 a b c a Wall embedded pipe b Putty c Wall hole cover 4 After completing wiring refrigerant piping and drain piping do NOT forget to seal the gap with putty 5 2 3 To remove the pipe port cover To connect the piping on r...

Page 9: ...milarly qualified persons in order to avoid a hazard WARNING Do NOT connect the power supply to the indoor unit This could result in electrical shock or fire WARNING Do NOT use locally purchased electrical parts inside the product Do NOT branch the power supply for the drain pump etc from the terminal block This could result in electrical shock or fire WARNING Keep the interconnection wiring away ...

Page 10: ...sory f Bottom frame 5 5 2 To pass the pipes through the wall hole 1 Shape the refrigerant pipes along the pipe path marking on the mounting plate a b c c d e a Drain hose b Caulk this hole with putty or caulking material c Adhesive vinyl tape d Insulation tape e Mounting plate accessory NOTICE Do NOT bend refrigerant pipes Do NOT push the refrigerant pipes onto the bottom frame or the front grille...

Page 11: ...stallation of the unit first check the items listed below Once all checks are fulfilled the unit must be closed Power up the unit after it is closed You read the complete installation instructions as described in the installer reference guide The indoor units are properly mounted The outdoor unit is properly mounted Air inlet outlet Check that the air inlet and outlet of the unit is NOT obstructed...

Page 12: ...ing the air conditioner in Cooling mode in winter set it to test run operation using the following method For FTXP and ATXP units 1 Press and simultaneously 2 Press 3 Select 4 Press 5 Press to switch the system on Result Test run operation will stop automatically after about 30 minutes 6 To stop operation press For FTXF units 7 Press to switch the system on 8 Press the centre of and simultaneously...

Page 13: ... DS DIP SWITCH E H HEATER F U FU FOR CHARACTERISTICS FUSE REFER TO PCB INSIDE YOUR UNIT FG CONNECTOR FRAME GROUND H HARNESS H P LED V L PILOT LAMP LIGHT EMITTING DIODE HAP LIGHT EMITTING DIODE SERVICE MONITOR GREEN HIGH VOLTAGE HIGH VOLTAGE IES INTELLIGENT EYE SENSOR IPM INTELLIGENT POWER MODULE K R KCR KFR KHuR K M MAGNETIC RELAY L LIVE L COIL L R REACTOR M STEPPER MOTOR M C COMPRESSOR MOTOR M F ...

Page 14: ......

Page 15: ......

Page 16: ...LERİ SAN TİC A Ş İSTANBUL TÜRKİYE Tel 0216 453 27 00 Faks 0216 671 06 00 Çağrı Merkezi 444 999 0 Web www daikin com tr Gülsuyu Mahallesi Fevzi Çakmak Caddesi Burçak Sokak No 20 34848 Maltepe 3P519299 1H 2019 09 Copyright 2019 Daikin ...

Reviews: