5
Copyright 2022 by CyboEnergy
This photovoltaic rapid shutdown equipment (PVRSE) does
not perform all of the functions of a complete photovoltaic rapid
shutdown system (PVRSS). This PVRSE must be installed with
other equipment to form a complete PVRSS that meets the
requirements of NEC (NFPA 70) section 690.12 for controlled
conductors outside the array. Other equipment installed in or on
this PV system may adversely affect the operation of the
PVRSS. It is the responsibility of the installer to ensure that the
completed PV system meets the rapid shutdown functional
requirements. This equipment must be installed according to the
manufacturer’s installation instructions.
For roof mount PV systems, install the inverter within 1 foot
of the PV solar panel array. The Inverter enclosure to panel
substrate must have at least 0.5 inch (12.7 mm) open space.
Rapid Shutdown Instructions