Mounting instructions VacuStar WR 2500 / WR 3100 / WR 4000
Installation and assembly
34
The following figure shows a diagram of the radiator
arrangement. Also see page 24, Fig. 8.
Fig. 10: Radiator arrangement
1 Process water inlet from the reservoir
2 Process water outlet to the reservoir
Assembly
Observe the following points during installation:
Operate the radiator in the bypass flow if possible.
Ask CVS engineering for the circulating cooling water
quantity
Install the radiator stress-free on rubber elements.
Install the cooling water pump at the lowest point.
Use hoses that are temperature-resistant up to 100 °C.
Add antifreeze compound for ambient temperatures below
0 °C.
Recommended delivery rate of the water pump 5,200 l/h at
0.2 bar pressure loss
NOTE!
In order to prevent introduction of deposits or dirt
particles into the VacuStar WR with the industrial
water, we recommend installing a coarser filter
depending on the chosen cooler.